22708 W INGOMAR ST 91304
Certificate Information: 22708 W INGOMAR ST 91304
- Application / Permit
- 21047-20000-00349
- Plan Check / Job No.
- B21VN01892
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 32' POOL WITH A 7' X 7' SPA. PER STANDARD PLAN #268
- Permit Issued
- Issued on 3/24/2021
- Issuing Office
- Current Status
- CofO Issued on 7/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/4/2021 | MOHAMMAD ESMAILI |
| Corrections Issued | 3/4/2021 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/17/2021 | OMAR GARNICA |
| Issued | 3/24/2021 | APPLICANT |
| Building Plans Picked Up | 3/26/2021 | APPLICANT |
| CofO in Progress | 7/8/2021 | DAVID STEPANYAN |
| CofO Issued | 7/8/2021 | JOHN JANSON |
| Permit Finaled | 7/8/2021 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | M K Pools & Gaswork Inc; Lic. No.: 1024181-C53 | P O BOX 1251 SIMI VALLEY, CA 93062 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/11/2021 | Approved | DAVID STEPANYAN |
| Gas Piping or Gas Test | 5/11/2021 | Approved | DAVID STEPANYAN |
| Grounding or Bonding | 5/11/2021 | Partial Approval | DAVID STEPANYAN |
| Pool Piping | 5/11/2021 | Approved | DAVID STEPANYAN |
| Pre-Gunite | 5/11/2021 | Approved | DAVID STEPANYAN |
| Deck | 5/25/2021 | Approved | DAVID STEPANYAN |
| Enclosure/Fence | 6/7/2021 | Approved | DAVID STEPANYAN |
| Equipment Noise Level | 6/30/2021 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 7/6/2021 | Approved | DAVID STEPANYAN |
| Final | 7/6/2021 | Partial Approval | DAVID STEPANYAN |
| Grounding or Bonding | 7/6/2021 | Approved | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2021 | SGSOV Approved | DAVID STEPANYAN |
| Final | 7/8/2021 | OK to Issue CofO | DAVID STEPANYAN |