6262 N RESEDA BLVD 91335
Certificate Information: 6262 N RESEDA BLVD 91335
- Application / Permit
- 21047-20000-00305
- Plan Check / Job No.
- B21VN01631
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- REMODEL THE (E) POOL, NEW PLASTER, TILE, DECKING, RAILINGS, AND SPLIT THE DRAIN.
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- Current Status
- Permit Finaled on 4/1/2022
Permit Application Status History
| Submitted | 2/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2021 | LUIS RINCON |
| Plan Check Approved | 2/23/2021 | LUIS RINCON |
| Building Plans Picked Up | 2/25/2021 | APPLICANT |
| Issued | 3/18/2021 | APPLICANT |
| Permit Finaled | 4/1/2022 | KENNETH ROBERTS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pinnacle Pool & Spa Construction; Lic. No.: 793046-C53 | 2374 DUSAN STREET SIMI VALLEY, CA 93065 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/19/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Grounding or Bonding | 6/4/2021 | Partial Approval | CAMERON CHABAN |
| Rough-Electrical | 6/4/2021 | Approved | CAMERON CHABAN |
| Rough-Plumbing | 6/4/2021 | Approved | CAMERON CHABAN |
| Deck | 7/28/2021 | Approved | ANDREW DORSO |
| Grounding or Bonding | 7/28/2021 | Partial Inspection | ANDREW DORSO |
| Pool Piping | 7/28/2021 | Partial Inspection | ANDREW DORSO |
| Deck | 8/18/2021 | Approved | CAMERON CHABAN |
| Grounding or Bonding | 8/18/2021 | Approved | CAMERON CHABAN |
| Deputy Drilled-In Anchors | 9/13/2021 | Conditional Approval | JEFFREY DURAN |
| Rough-Plumbing | 9/22/2021 | Partial Approval | ROBERT DAVIS |
| Deck | 11/3/2021 | Partial Approval | DANIEL VARNUM |
| Enclosure/Fence | 11/3/2021 | Partial Approval | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Approved | KENNETH ROBERTS |
| Final | 3/24/2022 | Partial Approval | KENNETH ROBERTS |
| Final | 4/1/2022 | Permit Finaled | KENNETH ROBERTS |