16200 W DORILEE LANE 91436

Certificate Information: 16200 W DORILEE LANE 91436

Application / Permit
21047-20000-00299
Plan Check / Job No.
B21VN01590
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
REMODEL (E) POOL, ADD 7'-6" X 7'-6" SPA INSIDE POOL, NEW BAJA BENCH, REMOVE (E) STEPS AND SPLIT DRAINS W/ AUTO POOL COVER PER STANDARD PLAN #265
Permit Issued
Issued on 5/10/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 RAPHAEL ROSAS
Corrections Issued 2/25/2021 RAPHAEL ROSAS
Plan Check Approved 4/13/2021 RAPHAEL ROSAS
Issued 5/10/2021 APPLICANT
Building Plans Picked Up 8/13/2021 APPLICANT
CofO in Progress 1/12/2022 DAVID SANDOVAL
CofO Issued 8/27/2022 MICHAEL SMITH
Permit Finaled 8/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Specific Plan Cleared 3/19/2021 NOAH MCCOY
ZA Case Cleared 3/19/2021 NOAH MCCOY
ZA Case Cleared 3/19/2021 NOAH MCCOY
ZI Cleared 3/19/2021 NOAH MCCOY

Contact Information

Contractor Owner-Builder       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 5/12/2021 Approved VINCENT HANLEY
Pre-Gunite 5/12/2021 Corrections Issued VINCENT HANLEY
Rough-Plumbing 5/12/2021 Approved VINCENT HANLEY
Pool Piping 5/17/2021 Approved RONALD COWAN
Pre-Gunite 5/17/2021 Approved RONALD COWAN
Rough-Plumbing 5/17/2021 Approved RONALD COWAN
Gas Piping or Gas Test 5/26/2021 Approved RONALD COWAN
Deck 7/20/2021 Corrections Issued RONALD COWAN
Deputy Drilled-In Anchors 8/9/2021 Approved RONALD COWAN
Pre-Gunite 8/10/2021 Approved RONALD COWAN
Enclosure/Fence 9/3/2021 Approved RONALD COWAN
Final 10/19/2021 Corrections Issued RONALD COWAN
Final 12/12/2021 Off-Hour Fees Due
Final 12/20/2021 Not Ready for Inspection DAVID SANDOVAL
Equipment Noise Level 12/23/2021 Approved ALFREDO FLORES
Final 1/11/2022 OK to Issue CofO DAVID SANDOVAL