10505 W BLOOMFIELD ST 91602
Certificate Information: 10505 W BLOOMFIELD ST 91602
- Application / Permit
- 21047-20000-00277
- Plan Check / Job No.
- B21VN01435
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 26' X 14' SWIMMING POOL WITH INTERIOR 6' X 6' SPA PER STANDARD PLAN #268.
- Permit Issued
- Issued on 2/25/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2021 | ROSENDO MEDINA |
| Corrections Issued | 2/20/2021 | ROSENDO MEDINA |
| Plan Check Approved | 2/25/2021 | ROSENDO MEDINA |
| Issued | 2/25/2021 | APPLICANT |
| Building Plans Picked Up | 3/1/2021 | APPLICANT |
| CofO in Progress | 5/14/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 5/14/2021 | ARTHUR SARGSYAN |
| CofO in Progress | 5/14/2021 | MICHAEL SMITH |
| CofO Issued | 5/14/2021 | MICHAEL SMITH |
| Permit Finaled | 5/14/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/11/2021 | Conditional Approval | THOMAS FINNILA |
| Enclosure/Fence | 4/16/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Grounding or Bonding | 4/16/2021 | Corrections Issued | THOMAS FINNILA |
| Deck | 4/22/2021 | Approved | THOMAS FINNILA |
| Enclosure/Fence | 4/22/2021 | Approved | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 4/30/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 4/30/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Pre-Gunite | 4/30/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Equipment Noise Level | 5/7/2021 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 5/13/2021 | Approved | ARTHUR SARGSYAN |
| Final | 5/13/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Pre-Gunite | 5/13/2021 | Approved | ARTHUR SARGSYAN |