2519 N CHISLEHURST PL 90027
Certificate Information: 2519 N CHISLEHURST PL 90027
- Application / Permit
- 21047-20000-00271
- Plan Check / Job No.
- B21VN01395
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW IIREGULAR SHAPE 28' X 11'6" POOL WITH 8'6" X 8' SPA ON PILES. ALL WORK PER ENGINEER - 1 OF 2
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2021 | PARISA ZAHABI |
| Corrections Issued | 2/17/2021 | PARISA ZAHABI |
| Quality Review Completed | 2/17/2021 | OMID HEDAYAT |
| Plan Check Approved | 3/17/2021 | PARISA ZAHABI |
| Building Plans Picked Up | 3/18/2021 | APPLICANT |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 8/13/2021 | JOSEPH MCGARRY |
| Permit Finaled | 8/25/2021 | RONALD MYRICK |
| CofO Issued | 8/25/2021 | RONALD MYRICK |
| Permit Finaled | 8/25/2021 | RONALD MYRICK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbander,, Mohamad Nabil; Lic. No.: C61250 | 205 SAINT VINCENT IRVINE, CA 92618 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/5/2021 | Partial Approval | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 5/20/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 5/24/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 6/1/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 6/1/2021 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 6/1/2021 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 6/1/2021 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Partial Approval | SCOTT FINNILA |
| Deck | 7/2/2021 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 7/2/2021 | Corrections Issued | JOSEPH MCGARRY |
| Enclosure/Fence | 7/9/2021 | Partial Approval | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Not Ready | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Not Ready | JOSEPH MCGARRY |
| Final | 7/30/2021 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 8/10/2021 | Approved | JOSEPH MCGARRY |
| Final | 8/10/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | JOSEPH MCGARRY |