5412 N SEPULVEDA BLVD 91411
Certificate Information: 5412 N SEPULVEDA BLVD 91411
- Application / Permit
- 21047-20000-00257
- Plan Check / Job No.
- B21VN01311
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- Apartment
- Primary Use
- (4) Pool/Spa - Public
- Work Description
- REMODEL (E) PUBLIC SWIMMING POOL FOR (E) APARTMENT BUILDING - REPLASTER, REPLUMB AND REPLACE HANDRAILS. INSTALL NEW GLASS RAILING SYSTEM PER ENGINEER.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/20/2023
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 2/17/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 2/17/2021 | JEROME MAGAT PALMA |
| No Progress | 2/17/2021 | JEROME MAGAT PALMA |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| Permit Finaled | 11/20/2023 | ANDREW DORSO |
Permit Application Clearance Information
| Public Swimming Pool approval | Cleared | 2/17/2021 | LACDHS APPROVED |
| ZA Case | Cleared | 5/7/2021 | DANG NGUYEN |
Contact Information
| Contractor | Klear Sand; Lic. No.: 1040426-C53 | 634 N ALLYN AVE ONTARIO, CA 91764 |
| Engineer | Horner,, Craig Michael; Lic. No.: C84674 | 3112 LEATHA WAY SACRAMENTO, CA 95821 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Final | 11/15/2021 | No Access for Inspection | DANIEL VARNUM |
| PLUMBING-Final | 11/17/2021 | Not Ready for Inspection | ANDREW DORSO |
| PLUMBING-Final | 11/19/2021 | Corrections Issued | ANDREW DORSO |
| Rough-Mechanical | 11/19/2021 | Corrections Issued | ANDREW DORSO |
| Pre-Gunite | 3/9/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Other (see comments) | 4/8/2022 | Conditional Approval | ANDREW DORSO |
| ELECTRICAL-Final | 4/22/2022 | Not Ready for Inspection | DANIEL VARNUM |
| PLUMBING-Final | 4/22/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Gunite | 6/24/2022 | Partial Inspection | ANDREW DORSO |
| Pre-Gunite | 6/24/2022 | Approved | ANDREW DORSO |
| Final | 2/17/2023 | No Access for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 2/17/2023 | No Access for Inspection | BRIAN KELLY |
| Final | 3/28/2023 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 3/28/2023 | SGSOV Not Ready | ANDREW DORSO |
| Special/Order Compliance | 3/28/2023 | No Access for Inspection | BRIAN KELLY |
| Final | 5/25/2023 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Not Ready | BRIAN KELLY |
| PLUMBING-Final | 6/8/2023 | No Access for Inspection | DEANDRE HOFFMAN |
| Final | 6/27/2023 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | ANDREW DORSO |
| Final | 10/27/2023 | Corrections Issued | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 10/27/2023 | SGSOV Approved | DEANDRE HOFFMAN |
| Final | 11/13/2023 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Final | 11/20/2023 | Permit Finaled | ANDREW DORSO |