2192 N BANYAN DR 90049
Certificate Information: 2192 N BANYAN DR 90049
- Application / Permit
- 21047-20000-00251
- Plan Check / Job No.
- B21VN01286
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 26'-0" x 18'-0" POOL WITH 6'-0" x 9'-0" SPA PER LA CITY STANDARD PLAN# 270
- Permit Issued
- Issued on 5/7/2021
- Issuing Office
- Current Status
- CofO Issued on 6/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/19/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 2/21/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 4/7/2021 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 4/23/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 5/7/2021 | SARKIS HARABEDIAN |
| Issued | 5/7/2021 | APPLICANT |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| CofO in Progress | 6/9/2022 | JUAN VALENZUELA |
| Permit Finaled | 6/9/2022 | DANIEL ORRANTE |
| CofO Issued | 6/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 6/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2021 | CATHERINE ADROVER |
| Watercourse | Cleared | 3/17/2021 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 5/7/2021 | SARKIS HARABEDIAN |
Contact Information
| Contractor | Way To Go Builders; Lic. No.: 1043721-B | 6700 FALLBROOK AVE STE 133 WEST HILLS, CA 91307 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2021 | Approved | JUAN VALENZUELA |
| FLOOD-Elevation Certificate | 6/23/2021 | Approved | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 6/23/2021 | Approved | JUAN VALENZUELA |
| Pre-Gunite | 6/23/2021 | Approved | JUAN VALENZUELA |
| Rough-Plumbing | 6/23/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Shotcrete | 6/28/2021 | Conditional Approval | JUAN VALENZUELA |
| Enclosure/Fence | 1/12/2022 | Approved | JUAN VALENZUELA |
| Final | 1/12/2022 | Corrections Issued | JUAN VALENZUELA |
| Pool Equipment Noise Test | 5/10/2022 | Approved | JAMES VORHIS |
| Final | 5/18/2022 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 5/18/2022 | SGSOV Approved | JUAN VALENZUELA |
| Final | 6/7/2022 | OK to Issue CofO | JUAN VALENZUELA |