9211 W NIGHTINGALE DR 90069
Certificate Information: 9211 W NIGHTINGALE DR 90069
- Application / Permit
- 21047-20000-00242
- Plan Check / Job No.
- B21VN01241
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL (47'-4" X 13'-4") & SPA (8'-7" X9'-4") PER LA CITY STD PLAN #265
- Permit Issued
- Issued on 11/17/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | NILOOFAR MEHRAIN |
| Corrections Issued | 2/25/2021 | NILOOFAR MEHRAIN |
| Quality Review Completed | 3/1/2021 | CHON CHIO KUO |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Applicant returned to address corrections | 4/9/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/9/2021 | NILOOFAR MEHRAIN |
| No Progress | 4/9/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/18/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 8/18/2021 | NILOOFAR MEHRAIN |
| Issued | 11/17/2021 | APPLICANT |
| CofO in Progress | 6/12/2023 | RAUL BARAJAS |
| CofO Issued | 6/25/2023 | DEROLD HAUFF |
| Permit Finaled | 6/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/24/2021 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Precision Building & Development Inc; Lic. No.: 859758-B | 11628 SANTA MONICA BLVD #204 LOS ANGELES, CA 90025 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
| Geologist | Schick,, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | RAUL BARAJAS |
| Final | 5/22/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Pre-Gunite | 5/22/2023 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 6/6/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 6/9/2023 | OK to Issue CofO | RAUL BARAJAS |