11233 W MONTANA AVE 90049

Certificate Information: 11233 W MONTANA AVE 90049

Application / Permit
21047-20000-00228
Plan Check / Job No.
B21VN01207
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 13'-8" X 25' IRREG SHAPED SWIMMING POOL AND 6'-1" X 5'-9" IRREG SHAPED SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Issued on 10/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2021 APPLICANT
Assigned to Plan Check Engineer 2/10/2021 JEROME MAGAT PALMA
Corrections Issued 2/14/2021 JEROME MAGAT PALMA
Plan Check Approved 5/17/2021 JEROME MAGAT PALMA
Building Plans Picked Up 5/19/2021 APPLICANT
Issued 5/26/2021 APPLICANT
CofO in Progress 9/20/2022 CARLOS MATAMOROS
CofO in Progress 9/20/2022 CARLOS MATAMOROS
Permit Finaled 10/5/2022 DANIEL ORRANTE
CofO Issued 10/5/2022 DANIEL ORRANTE
Permit Finaled 10/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/13/2021 JEROME MAGAT PALMA

Contact Information

Contractor Way To Go Builders; Lic. No.: 1043721-B 6700 FALLBROOK AVE STE 133      WEST HILLS, CA 91307
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2021 Corrections Issued CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 11/19/2021 Corrections Issued CARLOS MATAMOROS
Grounding or Bonding 11/19/2021 Approved CARLOS MATAMOROS
Rough-Plumbing 11/23/2021 Partial Approval BRENDAN LOONEY
Grounding or Bonding 12/2/2021 Approved CARLOS MATAMOROS
Pre-Gunite 12/2/2021 Corrections Issued CARLOS MATAMOROS
Deputy Shotcrete 12/10/2021 Conditional Approval CARLOS MATAMOROS
Enclosure/Fence 4/18/2022 Not Ready for Inspection CARLOS MATAMOROS
Enclosure/Fence 4/20/2022 Not Ready for Inspection CHRISTOPHER WILSON
Enclosure/Fence 4/27/2022 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/21/2022 Corrections Issued CARLOS MATAMOROS
Final 6/21/2022 Corrections Issued CARLOS MATAMOROS
Pre-Gunite 6/21/2022 Partial Approval CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/21/2022 SGSOV Approved CARLOS MATAMOROS
Equipment Noise Level 6/23/2022 Approved JUSTIN CURTIS
Excavation/Setback/Form/Re-Bar 7/6/2022 Partial Approval CARLOS MATAMOROS
Final 7/6/2022 Corrections Issued CARLOS MATAMOROS
Pre-Gunite 7/6/2022 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 7/20/2022 Approved CARLOS MATAMOROS
Final 7/20/2022 Corrections Issued CARLOS MATAMOROS
Final 7/25/2022 Corrections Issued PATRICK QUALEY
Final 8/2/2022 Corrections Issued MICHAEL PELHAM
Final 8/16/2022 Conditional Approval MICHAEL PELHAM
Final 9/20/2022 OK to Issue CofO CARLOS MATAMOROS