5702 N NATICK AVE 91411
Certificate Information: 5702 N NATICK AVE 91411
- Application / Permit
- 21047-20000-00198
- Plan Check / Job No.
- B21VN01044
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 14'x 26' POOL PER STANDARD PLAN 268
- Permit Issued
- Issued on 10/10/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | SELLA BENYAMIN |
| Corrections Issued | 2/25/2021 | SELLA BENYAMIN |
| Quality Review Completed | 2/26/2021 | STEVEN KIM |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| Plan Check Approved | 10/8/2021 | SELLA BENYAMIN |
| Issued | 10/10/2021 | APPLICANT |
| CofO in Progress | 8/3/2022 | RICHARD DOCKUS |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
| CofO Issued | 8/27/2022 | DEROLD HAUFF |
| Permit Finaled | 8/27/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | America Green Builders; Lic. No.: 1020657-B | 6601 ALCOVE AVE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 2/16/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Pre-Gunite | 2/16/2022 | Corrections Issued | MICHAEL TEMPLE |
| Rough-Electrical | 2/16/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Rough-Plumbing | 2/16/2022 | Not Ready for Inspection | MICHAEL TEMPLE |
| Gas Piping or Gas Test | 2/22/2022 | Approved | RICHARD DOCKUS |
| Grounding or Bonding | 2/22/2022 | Approved | RICHARD DOCKUS |
| Pool Piping | 2/22/2022 | Approved | RICHARD DOCKUS |
| Pre-Gunite | 2/22/2022 | Approved | RICHARD DOCKUS |
| Rough-Electrical | 2/22/2022 | Approved | RICHARD DOCKUS |
| Rough-Plumbing | 2/22/2022 | Approved | RICHARD DOCKUS |
| Deputy Shotcrete | 2/23/2022 | No Access for Inspection | RICHARD DOCKUS |
| Deck | 5/18/2022 | Corrections Issued | MICHAEL TEMPLE |
| Deck | 5/23/2022 | Approved | RICHARD DOCKUS |
| Enclosure/Fence | 6/27/2022 | Corrections Issued | RICHARD DOCKUS |
| Enclosure/Fence | 7/1/2022 | Approved | RICHARD DOCKUS |
| Pool Equipment Noise Test | 7/5/2022 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Approved | RICHARD DOCKUS |
| Final | 7/12/2022 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Approved | RICHARD DOCKUS |
| Final | 8/2/2022 | OK to Issue CofO | RICHARD DOCKUS |