23043 W CANZONET ST 91367

Certificate Information: 23043 W CANZONET ST 91367

Application / Permit
21047-20000-00192
Plan Check / Job No.
B21VN01017
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
REMODEL (E) 20'x40' POOL, ADD (N) 8'x8' SPA IN THE DEEP END OF THE POOL, ADD NEW BAR TABLE AND STOOLS, AND MAKE THE POOL SHALLOWER; POOL/SPA DESIGN PER STANDARD DETAIL #268
Permit Issued
Issued on 5/26/2021
Issuing Office
Current Status
CofO Issued on 1/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/18/2021 SEAN SHAHMIRI
Corrections Issued 2/26/2021 SEAN SHAHMIRI
Quality Review Completed 3/8/2021 OMID HEDAYAT
Building Plans Picked Up 3/10/2021 APPLICANT
Applicant returned to address corrections 4/19/2021 SEAN SHAHMIRI
Applicant returned to address corrections 5/26/2021 SEAN SHAHMIRI
Plan Check Approved 5/26/2021 SEAN SHAHMIRI
Issued 5/26/2021 APPLICANT
CofO in Progress 12/14/2021 TROY SANDERS
Permit Finaled 1/12/2022 JOHN JANSON
CofO Issued 1/12/2022 JOHN JANSON
Permit Finaled 1/12/2022 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/15/2021 SEAN SHAHMIRI

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2021 Approved TROY SANDERS
Rough-Electrical 7/23/2021 Approved TROY SANDERS
Rough-Plumbing 7/23/2021 Approved TROY SANDERS
Deputy Shotcrete 8/5/2021 Partial Approval TROY SANDERS
Deck 9/17/2021 Not Ready for Inspection TROY SANDERS
Deck 9/27/2021 Approved TROY SANDERS
Enclosure/Fence 11/9/2021 Approved TROY SANDERS
Equipment Noise Level 12/7/2021 Approved ALFREDO FLORES
Final 12/7/2021 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved TROY SANDERS
Final 12/14/2021 OK to Issue CofO TROY SANDERS
Special/Order Compliance 12/28/2021 Corrections Issued TROY SANDERS