22148 W CHASE ST 91304

Certificate Information: 22148 W CHASE ST 91304

Application / Permit
21047-20000-00172
Plan Check / Job No.
B21VN00855
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'-0"x 22'-0") POOL AND (7'-0"x 7'-0") SPA WITHIN. PER LA STD PLAN # 268, DETAIL#501.
Permit Issued
Issued on 4/6/2021
Issuing Office
Current Status
CofO Issued on 7/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2021 APPLICANT
Assigned to Plan Check Engineer 2/16/2021 TROY DEGUZMAN
Corrections Issued 2/16/2021 TROY DEGUZMAN
Plan Check Approved 4/5/2021 TROY DEGUZMAN
Issued 4/6/2021 APPLICANT
CofO in Progress 7/6/2021 DAVID STEPANYAN
CofO Issued 7/12/2021 JOHN JANSON
Permit Finaled 7/12/2021 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/16/2021 TROY DEGUZMAN
Construction within easement Cleared 3/25/2021 WALTER RAMIREZ

Contact Information

Contractor Doman Pools; Lic. No.: 802618-C53 887 PATRIOT DRIVE #F      MOORPARK, CA 93021
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/20/2021 Approved DAVID STEPANYAN
Pool Piping 4/20/2021 Approved DAVID STEPANYAN
Pre-Gunite 4/20/2021 Approved DAVID STEPANYAN
Deputy Shotcrete 4/21/2021 Conditional Approval DAVID STEPANYAN
Gas Piping or Gas Test 5/17/2021 Not Ready for Inspection DAVID STEPANYAN
Enclosure/Fence 6/7/2021 Approved DAVID STEPANYAN
Gas Piping or Gas Test 6/7/2021 Approved DAVID STEPANYAN
Pool Equipment Noise Test 6/17/2021 Approved ALFREDO FLORES
ELECTRICAL-Final 6/24/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Not Required DAVID STEPANYAN
ELECTRICAL-Final 7/6/2021 Approved DAVID STEPANYAN
Final 7/6/2021 OK to Issue CofO DAVID STEPANYAN
Grounding or Bonding 7/6/2021 Approved DAVID STEPANYAN