1020 N NORMAN PL 90049

Certificate Information: 1020 N NORMAN PL 90049

Application / Permit
21047-20000-00134
Plan Check / Job No.
B21VN00626
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 20' X 42' POOL W/ 8'-10" X 10' SPA PER STANDARD PLAN #268
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 11/24/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2021 RAPHAEL ROSAS
Corrections Issued 2/4/2021 RAPHAEL ROSAS
Applicant returned to address corrections 3/8/2021 RAPHAEL ROSAS
Applicant returned to address corrections 4/8/2021 RAPHAEL ROSAS
Plan Check Approved 4/21/2021 RAPHAEL ROSAS
Issued 4/22/2021 APPLICANT
Building Plans Picked Up 4/22/2021 APPLICANT
CofO in Progress 10/25/2021 CARLOS MATAMOROS
CofO in Progress 11/1/2021 CARLOS MATAMOROS
Permit Finaled 11/24/2021 DANIEL ORRANTE
CofO Issued 11/24/2021 DANIEL ORRANTE
Permit Finaled 11/24/2021 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/1/2021 TRACY TATE
ZA Case Cleared 3/12/2021 DANG NGUYEN
Watercourse Cleared 3/31/2021 MAHELET GEBEYHU
Grading Pre-Inspection Cleared 4/8/2021 RAPHAEL ROSAS

Contact Information

Contractor Exclusive Pools Inc; Lic. No.: 343762-C53 18017 CHATSWORTH ST      GRANADA HILLS, CA 91344
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Byer,, John W; Lic. No.: EG883 1649 PUEBLA DRIVE      GLENDALE, CA 91207

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Proofing Certificate 5/5/2021 Approved CARLOS MATAMOROS
Grounding or Bonding 5/5/2021 Approved CARLOS MATAMOROS
Pool Piping 5/5/2021 Approved CARLOS MATAMOROS
Pre-Gunite 5/5/2021 Conditional Approval CARLOS MATAMOROS
Pre-Gunite 5/7/2021 Approved CARLOS MATAMOROS
Deputy Shotcrete 5/19/2021 Conditional Approval CARLOS MATAMOROS
Gas Piping or Gas Test 6/18/2021 Approved CARLOS MATAMOROS
Rough-Electrical 6/18/2021 Approved CARLOS MATAMOROS
Rough-Plumbing 6/18/2021 Approved CARLOS MATAMOROS
Enclosure/Fence 8/2/2021 Not Ready for Inspection CARLOS MATAMOROS
Enclosure/Fence 8/9/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 8/10/2021 Approved CARLOS MATAMOROS
Equipment Noise Level 9/3/2021 Approved AGUSTIN ALVAREZMORALES
Excavation/Setback/Form/Re-Bar 9/10/2021 Approved CARLOS MATAMOROS
FLOOD-Elevation Certificate 9/10/2021 Approved CARLOS MATAMOROS
Final 9/10/2021 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/10/2021 SGSOV Not Ready CARLOS MATAMOROS
ELECTRICAL-Final 9/17/2021 Approved CARLOS MATAMOROS
Final 9/17/2021 Partial Approval CARLOS MATAMOROS
PLUMBING-Final 9/17/2021 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Approved CARLOS MATAMOROS
Final 10/12/2021 OK to Issue CofO CARLOS MATAMOROS