5016 E RANGE VIEW AVE 90042
Certificate Information: 5016 E RANGE VIEW AVE 90042
- Application / Permit
- 21047-20000-00110
- Plan Check / Job No.
- B21VN00579
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 12' x 15.75' POOL AND 6.25' x 12' SPA.
- Permit Issued
- Issued on 9/20/2021
- Issuing Office
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/22/2021 | LUIS RINCON |
| Corrections Issued | 2/24/2021 | LUIS RINCON |
| Applicant returned to address corrections | 4/30/2021 | LUIS RINCON |
| Applicant returned to address corrections | 6/15/2021 | LUIS RINCON |
| Plan Check Approved | 9/19/2021 | LUIS RINCON |
| Issued | 9/20/2021 | APPLICANT |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| CofO in Progress | 3/22/2022 | SCOTT FINNILA |
| CofO Issued | 3/24/2022 | DEROLD HAUFF |
| Permit Finaled | 3/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/24/2021 | LUIS RINCON |
| Miscellaneous | Cleared | 9/17/2021 | LUIS RINCON |
Contact Information
| Contractor | Pepe'S Pools Inc; Lic. No.: 1028041-C53 | 4817 YORK BLVD LOS ANGELES, CA 90042 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| Pool Piping | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| Pre-Gunite | 11/16/2021 | Approved | HAMIK HARTOUNIAN |
| Grounding or Bonding | 12/10/2021 | Approved | CRAIG VAUGHAN |
| Enclosure/Fence | 2/1/2022 | Corrections Issued | CRAIG VAUGHAN |
| Enclosure/Fence | 2/14/2022 | Approved | CRAIG VAUGHAN |
| Final | 2/24/2022 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/24/2022 | SGSOV Not Ready | SCOTT FINNILA |
| Final | 3/8/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 3/8/2022 | SGSOV Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/21/2022 | Approved | SCOTT FINNILA |
| Final | 3/21/2022 | OK to Issue CofO | SCOTT FINNILA |
| PLUMBING-Final | 3/22/2022 | Approved | SCOTT FINNILA |