3309 S MCLAUGHLIN AVE 90066
Certificate Information: 3309 S MCLAUGHLIN AVE 90066
- Application / Permit
- 21047-20000-00095
- Plan Check / Job No.
- B21VN00518
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 10'-6" X 20'-4" POOL W/ 5' X 6' SPA INSIDE PER STANDARD PLAN #268
- Permit Issued
- Issued on 2/16/2021
- Issuing Office
- Current Status
- CofO Issued on 8/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/28/2021 | RAPHAEL ROSAS |
| Issued | 2/16/2021 | APPLICANT |
| CofO in Progress | 8/30/2021 | KENNETH NAGLE |
| Permit Finaled | 8/30/2021 | KENNETH NAGLE |
| CofO Issued | 8/30/2021 | KENNETH NAGLE |
| Permit Finaled | 8/30/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/30/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | California Pools; Lic. No.: 185102-C53 | 901 CALLE AMANECER #115 SAN CLEMENTE, CA 92673 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/5/2021 | Corrections Issued | EVAN COOPER |
| Grounding or Bonding | 4/13/2021 | Partial Approval | KENNETH NAGLE |
| Pre-Gunite | 4/13/2021 | Corrections Issued | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 4/19/2021 | Not Ready for Inspection | EVAN COOPER |
| Grounding or Bonding | 4/19/2021 | Not Ready for Inspection | EVAN COOPER |
| Gunite | 4/19/2021 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Not Ready | EVAN COOPER |
| Pre-Gunite | 4/26/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Gunite | 5/3/2021 | Approved | EVAN COOPER |
| Enclosure/Fence | 7/6/2021 | Corrections Issued | JACK MATTILLO |
| Grounding or Bonding | 7/6/2021 | Not Ready for Inspection | JACK MATTILLO |
| Enclosure/Fence | 7/9/2021 | Approved | DONALD GALLAGHER |
| Gas Piping or Gas Test | 7/9/2021 | Approved | DONALD GALLAGHER |
| Pool Piping | 7/9/2021 | Approved | DONALD GALLAGHER |
| Excavation/Setback/Form/Re-Bar | 7/28/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 7/28/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 8/4/2021 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Approved | EVAN COOPER |
| Pool Equipment Noise Test | 8/9/2021 | Approved | JAMES VORHIS |
| Final | 8/11/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |