348 W AVENUE 41 90065

Certificate Information: 348 W AVENUE 41 90065

Application / Permit
21047-20000-00041
Plan Check / Job No.
B21VN00238
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18'-6" X 27' POOL W/ 7' X 7' SPA PER STANDARD PLAN #268
Permit Issued
Issued on 6/4/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2021 APPLICANT
Assigned to Plan Check Engineer 1/20/2021 RAPHAEL ROSAS
Corrections Issued 1/20/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/22/2021 RAPHAEL ROSAS
Applicant returned to address corrections 3/9/2021 RAPHAEL ROSAS
Applicant returned to address corrections 5/3/2021 RAPHAEL ROSAS
Issued 6/4/2021 APPLICANT
Building Plans Picked Up 6/9/2021 APPLICANT
CofO in Progress 3/10/2022 OSVALDO PARAMO
CofO in Progress 3/10/2022 OSVALDO PARAMO
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 1/27/2021 DYLAN LAWRENCE
ZI Cleared 1/27/2021 DYLAN LAWRENCE
Grading Pre-Inspection Cleared 6/4/2021 RAPHAEL ROSAS

Contact Information

Contractor Vargas Excavating Inc; Lic. No.: 639939-C53 501 SO REINO ROAD # 338      NEWBURY PARK, CA 91320
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 8/11/2021 Approved OSVALDO PARAMO
Deputy Shotcrete 8/16/2021 Conditional Approval OSVALDO PARAMO
Rough-Electrical 10/13/2021 Partial Approval OSVALDO PARAMO
Rough-Plumbing 10/13/2021 Partial Approval OSVALDO PARAMO
Grounding or Bonding 11/9/2021 Approved OSVALDO PARAMO
Enclosure/Fence 1/21/2022 Approved OSVALDO PARAMO
Pool Equipment Noise Test 2/1/2022 Approved ROBERT CHAVEZ
Excavation/Setback/Form/Re-Bar 2/10/2022 Approved OSVALDO PARAMO
Final 2/10/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Not Ready OSVALDO PARAMO
Final 2/15/2022 Not Ready for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready OSVALDO PARAMO
Final 3/7/2022 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Approved OSVALDO PARAMO