5950 W 74TH ST 90045

Certificate Information: 5950 W 74TH ST 90045

Application / Permit
21047-10000-02860
Plan Check / Job No.
B21LA24459
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POO AND SPA
Permit Issued
Issued on 7/14/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/25/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 KHEDER ALRAZAA
Corrections Issued 3/1/2022 KHEDER ALRAZAA
Quality Review Completed 3/9/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/11/2022 APPLICANT
Applicant returned to address corrections 5/3/2022 KHEDER ALRAZAA
Plan Check Approved 6/9/2022 KHEDER ALRAZAA
Issued 7/14/2022 APPLICANT
CofO in Progress 7/13/2026 MICHAEL LEWIS
Permit Finaled 7/14/2026 RICHARD STEINBACH
CofO Issued 7/14/2026 RICHARD STEINBACH
Permit Finaled 7/14/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/31/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12631 IMPERIAL HWY F-230      SANTA FE SPRINGS, CA 90670

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/11/2026 No Access for Inspection ANTHONY EGSON
Final 6/11/2026 No Access for Inspection ANTHONY EGSON
Pre-Gunite 6/11/2026 No Access for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/11/2026 SGSOV Not Ready ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 6/29/2026 Approved MICHAEL LEWIS
Final 6/29/2026 Corrections Issued MICHAEL LEWIS
Pre-Gunite 6/29/2026 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 6/29/2026 SGSOV Not Ready MICHAEL LEWIS
Final 7/9/2026 OK to Issue CofO MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/9/2026 SGSOV Approved MICHAEL LEWIS