10901 W SAVONA ROAD 90077

Certificate Information: 10901 W SAVONA ROAD 90077

Application / Permit
21047-10000-02852
Plan Check / Job No.
B21LA24406
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool/spa
Permit Issued
Issued on 10/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 12/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 TU HUA
Corrections Issued 1/28/2022 TU HUA
Quality Review Completed 2/7/2022 SAI KHUM
Building Plans Picked Up 2/9/2022 APPLICANT
Applicant returned to address corrections 7/22/2022 TU HUA
Applicant returned to address corrections 7/29/2022 TU HUA
Applicant returned to address corrections 8/17/2022 TU HUA
Applicant returned to address corrections 8/31/2022 TU HUA
Applicant returned to address corrections 9/7/2022 TU HUA
Applicant returned to address corrections 9/14/2022 TU HUA
Plan Check Approved 10/7/2022 TU HUA
Issued 10/7/2022 APPLICANT
CofO in Progress 12/5/2024 CHRISTOPHER WILSON
Permit Finaled 12/9/2024 RICHARD STEINBACH
CofO Issued 12/9/2024 RICHARD STEINBACH
Permit Finaled 12/9/2024 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 2/4/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/7/2022 DINAH GARIN
Grading Pre-Inspection Cleared 9/14/2022 TU HUA

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Romm Builders Inc; Lic. No.: 779702-B 5746 RHODES AVE      VALLEY VILLAGE, CA 91607

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 12/16/2022 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 12/19/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Other (see comments) 12/20/2022 Conditional Approval MICHAEL PELHAM
Piling/Pier/Caisson 2/7/2023 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 2/8/2023 Partial Approval CARLOS MATAMOROS
Deputy Other (see comments) 2/9/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/2/2023 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 3/2/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/24/2023 Not Ready for Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 3/24/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 3/29/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 3/29/2023 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 3/29/2023 Partial Inspection MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 4/6/2023 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 4/27/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/3/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Shotcrete 5/11/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 5/12/2023 Not Ready for Inspection CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/17/2023 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 5/19/2023 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 5/26/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/26/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/26/2023 Not Ready for Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/20/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 7/6/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/6/2023 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 7/19/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/19/2023 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/19/2023 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 7/24/2023 Conditional Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 8/17/2023 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 8/17/2023 Corrections Issued CHRISTOPHER WILSON
Deputy Other (see comments) 8/28/2023 Conditional Approval MICHAEL PELHAM
Grounding or Bonding 8/29/2023 Partial Approval CHRISTOPHER WILSON
Pool Piping 8/29/2023 Approved CHRISTOPHER WILSON
Pre-Gunite 8/29/2023 Approved CHRISTOPHER WILSON
Rough-Electrical 8/29/2023 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 8/29/2023 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 9/1/2023 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 9/14/2023 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/14/2023 Partial Approval CHRISTOPHER WILSON
Grounding or Bonding 9/12/2024 Approved CARLOS MATAMOROS
Enclosure/Fence 11/8/2024 Corrections Issued STEPHANIE SWANSON
Enclosure/Fence 11/13/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 12/2/2024 Approved CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 12/2/2024 Approved CHRISTOPHER WILSON
Final 12/2/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 12/2/2024 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved CHRISTOPHER WILSON
Final 12/4/2024 OK to Issue CofO CHRISTOPHER WILSON