11831 W CHAPARAL ST 90049
Certificate Information: 11831 W CHAPARAL ST 90049
- Application / Permit
- 21047-10000-02842
- Plan Check / Job No.
- B21LA24258
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13' X 32' POOL PER STANDARD SWIMMING PLAN #254 AND ENGINEERING STR. CALC.
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 1/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/16/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/26/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/28/2022 | APPLICANT |
| Plan Check Approved | 3/15/2022 | MAHNAZ NOURHASHEMI |
| Issued | 4/4/2022 | APPLICANT |
| CofO in Progress | 11/15/2024 | CARLOS MATAMOROS |
| CofO Issued | 1/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 2/3/2022 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 3/15/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 6/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 6/27/2023 | Conditional Approval | CARLOS MATAMOROS |
| Deputy Shotcrete | 7/5/2023 | Conditional Approval | MICHAEL PELHAM |
| Pre-Gunite | 7/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| Gas Piping or Gas Test | 10/2/2023 | Corrections Issued | CARLOS MATAMOROS |
| Rough-Electrical | 10/2/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 10/5/2023 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 10/5/2023 | Approved | CARLOS MATAMOROS |
| Deck | 3/27/2024 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 7/31/2024 | Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 9/12/2024 | Approved | EUSEBIO GUZMAN |
| ELECTRICAL-Final | 9/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Approved | CARLOS MATAMOROS |
| Final | 9/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 9/18/2024 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 9/18/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 10/11/2024 | Corrections Issued | CARLOS MATAMOROS |
| Final | 10/30/2024 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/15/2024 | Approved | CARLOS MATAMOROS |
| Final | 11/15/2024 | OK to Issue CofO | CARLOS MATAMOROS |