1553 S GLENDON AVE 90024
Certificate Information: 1553 S GLENDON AVE 90024
- Application / Permit
- 21047-10000-02801
- Plan Check / Job No.
- B21LA23945
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA AT REAR (1 OF 4)
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/6/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | KEVIN MORALES |
| Corrections Issued | 1/18/2022 | KEVIN MORALES |
| Quality Review Completed | 1/20/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Plan Check Approved | 7/20/2022 | KEVIN MORALES |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 1/6/2026 | MICHAEL ALLEN |
| Permit Finaled | 1/6/2026 | RICHARD STEINBACH |
| CofO Issued | 1/6/2026 | RICHARD STEINBACH |
| Permit Finaled | 1/6/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 1/17/2022 | KEVIN MORALES |
| Grading Pre-Inspection | Cleared | 1/17/2022 | KEVIN MORALES |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 2/15/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Syg Builders Llc; Lic. No.: 1093375-B | 1340 BENEDICT CANYON BEVERLY HILLS, CA 90210 |
| Engineer | Ariannia,, Shawn; Lic. No.: GE2824 | 1453 LOOKOUT CT UPLAND, CA 91784 |
| Engineer | Lee,, Giang Cam; Lic. No.: C87598 | 2819 GRANADA AVE EL MONTE, CA 91733 |
| Engineer | Vahdat,, Shahram; Lic. No.: C47934 | 4333 EMPRESS AVE ENCINO, CA 91436 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 7/21/2023 | Approved | JEREMY TODD |
| Excavation/Setback/Form/Re-Bar | 7/27/2023 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 7/27/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Gunite | 8/23/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Gunite | 9/11/2023 | Approved | MEL KHACHATOURIAN |
| Deputy Shotcrete | 9/12/2023 | No Access for Inspection | MEL KHACHATOURIAN |
| Deck | 10/24/2023 | Partial Approval | MICHAEL PELHAM |
| Deck | 12/19/2023 | Approved | BEN MOLSTAD |
| Enclosure/Fence | 12/19/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Grounding or Bonding | 12/19/2023 | Approved | BEN MOLSTAD |
| Pool/Spa Cover | 12/19/2023 | Approved | BEN MOLSTAD |
| Enclosure/Fence | 7/9/2024 | Corrections Issued | KIRK SANDERS |
| Enclosure/Fence | 8/15/2024 | Approved | KIRK SANDERS |
| Final | 8/15/2024 | Not Ready for Inspection | KIRK SANDERS |
| Equipment Noise Level | 9/17/2024 | Not Ready for Inspection | ANDEY CHAPARRO |
| Pool Equipment Noise Test | 9/19/2024 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 7/17/2025 | Approved | DANIEL VERA |
| Final | 7/17/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Not Ready | DANIEL VERA |
| ELECTRICAL-Final | 11/20/2025 | Approved | MICHAEL ALLEN |
| Final | 11/20/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2025 | SGSOV Approved | MICHAEL ALLEN |
| Final | 12/9/2025 | Conditional Approval | MICHAEL ALLEN |
| Final | 12/17/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 1/5/2026 | OK to Issue CofO | MICHAEL ALLEN |