17701 W ARVIDA DR 91344
Certificate Information: 17701 W ARVIDA DR 91344
- Application / Permit
- 21047-10000-02799
- Plan Check / Job No.
- B21LA23916
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED 12' X 40'-6" X 6' DEEP POOL BEHIND (E) SFD PER STANDARD PLAN #268 AND ENGINEERED DETAIL #60 1 OF 2
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 5/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/4/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 1/5/2022 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| Plan Check Approved | 1/21/2022 | LAWRENCE QUIRANTE |
| Issued | 1/25/2022 | APPLICANT |
| CofO in Progress | 5/5/2022 | DAVID SCANTLIN |
| CofO Issued | 5/10/2022 | MICHAEL SMITH |
| Permit Finaled | 5/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/8/2021 | CHARLES POWELL |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C35 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/9/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Gunite | 2/18/2022 | Approved | DAVID SCANTLIN |
| Rough-Plumbing | 2/18/2022 | Approved | DAVID SCANTLIN |
| Deck | 3/14/2022 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 4/4/2022 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 4/18/2022 | Approved | DAVID SCANTLIN |
| Final | 4/18/2022 | Corrections Issued | DAVID SCANTLIN |
| Pool Equipment Noise Test | 4/18/2022 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Approved | DAVID SCANTLIN |
| Final | 5/4/2022 | OK to Issue CofO | DAVID SCANTLIN |