11619 N HUNNEWELL AVE 91342

Certificate Information: 11619 N HUNNEWELL AVE 91342

Application / Permit
21047-10000-02610
Plan Check / Job No.
B21LA22429
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL 13X27 AND NEW SPA 18" ABOVE THE GROUND 6X6 PER LA CITY STANDARD PLAN #268. NEW POOL EQUIPMENT
Permit Issued
Issued on 12/31/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/30/2021 APPLICANT
Assigned to Plan Check Engineer 12/1/2021 RACHEL BEYENE
Corrections Issued 12/1/2021 RACHEL BEYENE
Plan Check Approved 12/28/2021 DANIEL SANJUAN
Issued 12/31/2021 APPLICANT
Building Plans Picked Up 1/6/2022 APPLICANT
CofO in Progress 9/2/2022 MICHEL ABAJAN
Permit Finaled 9/3/2022 DEROLD HAUFF
Permit Finaled 9/3/2022 DEROLD HAUFF
CofO Issued 9/3/2022 DEROLD HAUFF

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Premier Pool Plastering; Lic. No.: 625132-C35 14520 FOOTHILL BLVD      SYLMAR, CA 91342

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/4/2022 Corrections Issued MICHEL ABAJAN
Pre-Gunite 3/9/2022 Corrections Issued MICHEL ABAJAN
Gas Piping or Gas Test 3/30/2022 Not Ready for Inspection MICHEL ABAJAN
Grounding or Bonding 3/30/2022 Not Ready for Inspection MICHEL ABAJAN
Pool Piping 3/30/2022 Not Ready for Inspection MICHEL ABAJAN
Pre-Gunite 3/30/2022 Not Ready for Inspection MICHEL ABAJAN
Gas Piping or Gas Test 4/27/2022 Approved MICHEL ABAJAN
Grounding or Bonding 4/27/2022 Approved MICHEL ABAJAN
Pool Piping 4/27/2022 Approved MICHEL ABAJAN
Pre-Gunite 4/27/2022 Approved MICHEL ABAJAN
Deck 7/5/2022 Approved ARAM AVEDISIAN
Enclosure/Fence 7/15/2022 Corrections Issued MICHEL ABAJAN
Pool Equipment Noise Test 7/28/2022 Approved FELIPE PENICHE
Final 8/3/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 8/3/2022 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Not Ready MICHEL ABAJAN
Final 8/30/2022 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Approved MICHEL ABAJAN