1417 N HAZELWOOD AVE 90041

Certificate Information: 1417 N HAZELWOOD AVE 90041

Application / Permit
21047-10000-02548
Plan Check / Job No.
B21LA21833
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN#268
Permit Issued
Issued on 8/5/2022
Issuing Office
Metro
Current Status
CofO Issued on 7/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/23/2021 GEORGE ALVAREZ
Corrections Issued 11/23/2021 GEORGE ALVAREZ
Applicant returned to address corrections 2/20/2022 ZAW HAN
Building Plans Picked Up 2/24/2022 APPLICANT
Applicant returned to address corrections 5/26/2022 KHUONG TRUONG
Plan Check Approved 8/5/2022 MINA HABILI
Issued 8/5/2022 APPLICANT
CofO in Progress 7/8/2023 CRAIG VAUGHAN
CofO in Progress 7/8/2023 CRAIG VAUGHAN
Permit Finaled 7/16/2023 DEROLD HAUFF
CofO Issued 7/16/2023 DEROLD HAUFF
Permit Finaled 7/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/5/2022 GEORGE ALVAREZ

Contact Information

Architect Adrianzen-Vasquez,, Jose A; Lic. No.: C25674 11083 DEER CANYON DR      RANCHO CUCAMONGA, CA 91737
Contractor Owner-Builder       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 8/26/2022 Approved HAMIK HARTOUNIAN
Rough-Electrical 8/26/2022 Approved HAMIK HARTOUNIAN
Rough-Plumbing 8/26/2022 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 8/31/2022 Corrections Issued CRAIG VAUGHAN
Gas Piping or Gas Test 8/31/2022 Approved CRAIG VAUGHAN
Pool Piping 8/31/2022 Partial Approval CRAIG VAUGHAN
Rough-Electrical 8/31/2022 Partial Approval CRAIG VAUGHAN
Rough-Plumbing 8/31/2022 Partial Approval CRAIG VAUGHAN
Pre-Gunite 9/8/2022 Approved HAMIK HARTOUNIAN
Deputy Shotcrete 9/21/2022 Conditional Approval CRAIG VAUGHAN
Deck 10/25/2022 Approved JULIAN AMAYA
Deck 10/25/2022 Not Ready for Inspection CRAIG VAUGHAN
Grounding or Bonding 10/25/2022 Approved JULIAN AMAYA
Enclosure/Fence 12/30/2022 Corrections Issued CRAIG VAUGHAN
Enclosure/Fence 1/10/2023 Not Ready for Inspection CRAIG VAUGHAN
Enclosure/Fence 1/12/2023 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/28/2023 Approved BRIAN SULLIVAN
Final 2/28/2023 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 2/28/2023 SGSOV Approved BRIAN SULLIVAN
Pool Equipment Noise Test 3/6/2023 Approved ZEYDI STEWART
Final 3/13/2023 OK to Issue CofO CRAIG VAUGHAN