1047 N CHAUTAUQUA BLVD 90272

Certificate Information: 1047 N CHAUTAUQUA BLVD 90272

Application / Permit
21047-10000-02094
Plan Check / Job No.
B21LA17630
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA WITH WATER FEATURE PER STANDARD PLAN 270
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/20/2021 APPLICANT
Assigned to Plan Check Engineer 9/23/2021 SHANGQIN XIE
Corrections Issued 9/23/2021 SHANGQIN XIE
Building Plans Picked Up 9/28/2021 APPLICANT
Plan Check Approved 12/7/2021 JOSEPH RAFOLS
Issued 12/9/2021 APPLICANT
CofO in Progress 12/6/2023 ARAM AVEDISIAN
Permit Finaled 12/19/2023 DANIEL ORRANTE
CofO Issued 12/19/2023 DANIEL ORRANTE
Permit Finaled 12/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 12/3/2021 RIDWAN HARDY

Contact Information

Contractor J J P Construction Inc; Lic. No.: 960864-B 12555 VANOWEN STREET   2ND FLOOR OFC    NORTH HOLLYWOOD, CA 91605

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/5/2023 Approved OGANES TARAKHCHYAN
Grounding or Bonding 6/5/2023 Approved OGANES TARAKHCHYAN
Pre-Gunite 6/5/2023 Approved OGANES TARAKHCHYAN
Rough-Electrical 6/5/2023 Approved OGANES TARAKHCHYAN
Rough-Plumbing 6/5/2023 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 6/20/2023 No Access for Inspection KENNETH NAGLE
Grounding or Bonding 8/31/2023 Partial Approval STEPHANIE SWANSON
Enclosure/Fence 11/3/2023 Approved OGANES TARAKHCHYAN
Pool Equipment Noise Test 11/28/2023 Approved JAMES VORHIS
Final 11/29/2023 Corrections Issued ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Approved ARAM AVEDISIAN
Final 12/1/2023 Not Ready for Inspection ARAM AVEDISIAN
Final 12/6/2023 OK to Issue CofO ARAM AVEDISIAN