1047 N CHAUTAUQUA BLVD 90272
Certificate Information: 1047 N CHAUTAUQUA BLVD 90272
- Application / Permit
- 21047-10000-02094
- Plan Check / Job No.
- B21LA17630
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA WITH WATER FEATURE PER STANDARD PLAN 270
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2021 | SHANGQIN XIE |
| Corrections Issued | 9/23/2021 | SHANGQIN XIE |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| Plan Check Approved | 12/7/2021 | JOSEPH RAFOLS |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 12/6/2023 | ARAM AVEDISIAN |
| Permit Finaled | 12/19/2023 | DANIEL ORRANTE |
| CofO Issued | 12/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/3/2021 | RIDWAN HARDY |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/5/2023 | Approved | OGANES TARAKHCHYAN |
| Grounding or Bonding | 6/5/2023 | Approved | OGANES TARAKHCHYAN |
| Pre-Gunite | 6/5/2023 | Approved | OGANES TARAKHCHYAN |
| Rough-Electrical | 6/5/2023 | Approved | OGANES TARAKHCHYAN |
| Rough-Plumbing | 6/5/2023 | Approved | OGANES TARAKHCHYAN |
| Deputy Shotcrete | 6/20/2023 | No Access for Inspection | KENNETH NAGLE |
| Grounding or Bonding | 8/31/2023 | Partial Approval | STEPHANIE SWANSON |
| Enclosure/Fence | 11/3/2023 | Approved | OGANES TARAKHCHYAN |
| Pool Equipment Noise Test | 11/28/2023 | Approved | JAMES VORHIS |
| Final | 11/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 12/1/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 12/6/2023 | OK to Issue CofO | ARAM AVEDISIAN |