735 N ILIFF ST 90272
Certificate Information: 735 N ILIFF ST 90272
- Application / Permit
- 21047-10000-02084
- Plan Check / Job No.
- B21LA17546
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA WITH WATER FEATURE.
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 10/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2021 | RAHEL BEYENE |
| Corrections Issued | 9/20/2021 | RAHEL BEYENE |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| Plan Check Approved | 12/7/2021 | JOSEPH RAFOLS |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 9/29/2022 | KEVIN SARGSYAN |
| Permit Finaled | 10/4/2022 | DANIEL ORRANTE |
| CofO Issued | 10/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/3/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/3/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 12/7/2021 | RAHEL BEYENE |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/23/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/8/2022 | Approved | ANDREW NAVE |
| Grounding or Bonding | 3/8/2022 | Partial Approval | ANDREW NAVE |
| Pre-Gunite | 3/8/2022 | Corrections Issued | ANDREW NAVE |
| Rough-Electrical | 3/8/2022 | Partial Approval | ANDREW NAVE |
| Rough-Plumbing | 3/8/2022 | Partial Approval | ANDREW NAVE |
| Pre-Gunite | 4/8/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Gunite | 4/12/2022 | Approved | JOHN KIDWELL |
| Deputy Shotcrete | 4/22/2022 | Partial Approval | JOHN KIDWELL |
| Gas Piping or Gas Test | 6/3/2022 | Approved | JUAN VALENZUELA |
| Grounding or Bonding | 7/6/2022 | Partial Approval | JOHN KIDWELL |
| Enclosure/Fence | 9/9/2022 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 9/21/2022 | Approved | JAMES VORHIS |
| Final | 9/22/2022 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 9/28/2022 | OK to Issue CofO | KEVIN SARGSYAN |