345 N MARTEL AVE 90036
Certificate Information: 345 N MARTEL AVE 90036
- Application / Permit
- 21047-10000-02061
- Plan Check / Job No.
- B21LA17365
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 5' DEEP POOL AND 3.5' DEEP SPA (12'-6" X 20'-0") PER STANDARD #268.
- Permit Issued
- Issued on 11/23/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2021 | RAMA DABADGE |
| Corrections Issued | 9/20/2021 | RAMA DABADGE |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| Applicant returned to address corrections | 10/27/2021 | ZAW HAN |
| Plan Check Approved | 10/28/2021 | ZAW HAN |
| Issued | 11/23/2021 | APPLICANT |
| CofO in Progress | 8/11/2022 | MICHAEL LEWIS |
| CofO in Progress | 8/15/2022 | JOSEPH MCGARRY |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/2/2022 | Approved | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Corrections Issued | ADAM ESCOTO |
| Gas Piping or Gas Test | 4/5/2022 | Approved | CRAIG DAVIS |
| Grounding or Bonding | 4/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Pool Piping | 4/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Pre-Gunite | 4/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Rough-Electrical | 4/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Rough-Plumbing | 4/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 4/8/2022 | Approved | ARTHUR SARGSYAN |
| Grounding or Bonding | 4/8/2022 | Approved | ARTHUR SARGSYAN |
| Pool Piping | 4/8/2022 | Approved | ARTHUR SARGSYAN |
| Pre-Gunite | 4/8/2022 | Approved | ARTHUR SARGSYAN |
| Deck | 4/26/2022 | Corrections Issued | ADAM ESCOTO |
| Gunite | 4/26/2022 | Corrections Issued | ADAM ESCOTO |
| Deck | 5/12/2022 | Approved | ADAM ESCOTO |
| Grounding or Bonding | 5/12/2022 | Approved | ADAM ESCOTO |
| Enclosure/Fence | 7/15/2022 | Approved | ADAM ESCOTO |
| Pool Equipment Noise Test | 7/29/2022 | Approved | ROBERT CHAVEZ |
| Final | 8/9/2022 | OK to Issue CofO | JOSEPH MCGARRY |