2406 N KENILWORTH AVE 90039
Certificate Information: 2406 N KENILWORTH AVE 90039
- Application / Permit
- 21047-10000-01999
- Plan Check / Job No.
- B21LA16529
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL WITH AUTOMATIC POOL COVER PER STANDARD PLAN AND ENGINEERED DETAILS
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2021 | RAMA DABADGE |
| Corrections Issued | 9/3/2021 | RAMA DABADGE |
| Applicant returned to address corrections | 9/22/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 10/14/2021 | SHANGQIN XIE |
| Plan Check Approved | 12/2/2021 | GEORGE ALVAREZ |
| Issued | 12/6/2021 | APPLICANT |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| CofO in Progress | 8/17/2022 | JOSEPH MCGARRY |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/5/2021 | ALBERT TAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2021 | JEANETTE VONG |
Contact Information
| Contractor | Design Management And Construction Services; Lic. No.: 856999-C53 | 26007 HUNTINGTON LANE STE 7 VALENCIA, CA 91355 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/11/2022 | No Access for Inspection | CRAIG DAVIS |
| Gunite | 4/13/2022 | Approved | RUBEN SALAS |
| Deputy Shotcrete | 4/14/2022 | Conditional Approval | CRAIG DAVIS |
| Deck | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Pool Piping | 6/16/2022 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 7/29/2022 | Conditional Approval | JOSEPH MCGARRY |
| Enclosure/Fence | 8/3/2022 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 8/9/2022 | Approved | JOSEPH MCGARRY |
| Final | 8/9/2022 | Corrections Issued | JOSEPH MCGARRY |
| Pre-Gunite | 8/9/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Approved | JOSEPH MCGARRY |
| Equipment Noise Level | 8/10/2022 | Approved | ROBERT CHAVEZ |
| Final | 8/15/2022 | OK to Issue CofO | JOSEPH MCGARRY |