2406 N KENILWORTH AVE 90039

Certificate Information: 2406 N KENILWORTH AVE 90039

Application / Permit
21047-10000-01999
Plan Check / Job No.
B21LA16529
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL WITH AUTOMATIC POOL COVER PER STANDARD PLAN AND ENGINEERED DETAILS
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 RAMA DABADGE
Corrections Issued 9/3/2021 RAMA DABADGE
Applicant returned to address corrections 9/22/2021 GEORGE ALVAREZ
Applicant returned to address corrections 10/14/2021 SHANGQIN XIE
Plan Check Approved 12/2/2021 GEORGE ALVAREZ
Issued 12/6/2021 APPLICANT
Building Plans Picked Up 12/7/2021 APPLICANT
CofO in Progress 8/17/2022 JOSEPH MCGARRY
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 11/5/2021 ALBERT TAM
Eng Process Fee Ord 176,300 Cleared 11/10/2021 JEANETTE VONG

Contact Information

Contractor Design Management And Construction Services; Lic. No.: 856999-C53 26007 HUNTINGTON LANE STE 7      VALENCIA, CA 91355
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 4/11/2022 No Access for Inspection CRAIG DAVIS
Gunite 4/13/2022 Approved RUBEN SALAS
Deputy Shotcrete 4/14/2022 Conditional Approval CRAIG DAVIS
Deck 6/16/2022 Approved JOSEPH MCGARRY
Gas Piping or Gas Test 6/16/2022 Approved JOSEPH MCGARRY
Grounding or Bonding 6/16/2022 Approved JOSEPH MCGARRY
Pool Piping 6/16/2022 Approved JOSEPH MCGARRY
Enclosure/Fence 7/29/2022 Conditional Approval JOSEPH MCGARRY
Enclosure/Fence 8/3/2022 Approved JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 8/9/2022 Approved JOSEPH MCGARRY
Final 8/9/2022 Corrections Issued JOSEPH MCGARRY
Pre-Gunite 8/9/2022 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Approved JOSEPH MCGARRY
Equipment Noise Level 8/10/2022 Approved ROBERT CHAVEZ
Final 8/15/2022 OK to Issue CofO JOSEPH MCGARRY