2545 N HUTTON DR 90210
Certificate Information: 2545 N HUTTON DR 90210
- Application / Permit
- 21047-10000-01955
- Plan Check / Job No.
- B21LA16057
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | DANIEL YIP |
| Corrections Issued | 9/21/2021 | DANIEL YIP |
| Quality Review Completed | 9/29/2021 | ALLEN MANALANSAN |
| Building Plans Picked Up | 10/1/2021 | APPLICANT |
| Applicant returned to address corrections | 1/21/2022 | DANIEL YIP |
| Applicant returned to address corrections | 7/14/2022 | DANIEL YIP |
| Plan Check Approved | 8/3/2022 | DANIEL YIP |
| Issued | 8/3/2022 | APPLICANT |
| CofO in Progress | 2/5/2025 | SEAN HAUPT |
| CofO Issued | 2/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/14/2022 | DANIEL YIP |
| Miscellaneous | Cleared | 8/3/2022 | MARC WOERSCHING |
Contact Information
| Contractor | O'Connor T H Construction Inc; Lic. No.: 762763-B | 5535 BALBOA BLVD #220 ENCINO, CA 91316 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/12/2023 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/13/2023 | Partial Approval | CARLOS MATAMOROS |
| Pre-Gunite | 9/8/2023 | Corrections Issued | BRENDAN LOONEY |
| Pre-Gunite | 9/12/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Pre-Gunite | 9/19/2023 | Approved | BRENDAN LOONEY |
| Deputy Shotcrete | 9/22/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Approval | BRENDAN LOONEY |
| Deck | 12/18/2023 | Approved | BRENDAN LOONEY |
| Enclosure/Fence | 6/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| Enclosure/Fence | 9/16/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Approved | SEAN HAUPT |
| Final | 10/15/2024 | Corrections Issued | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | SEAN HAUPT |
| Final | 2/4/2025 | OK to Issue CofO | SEAN HAUPT |