7329 S TRASK AVE 90293

Certificate Information: 7329 S TRASK AVE 90293

Application / Permit
21047-10000-01711
Plan Check / Job No.
B21LA14085
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool per LA city standard plan #265 and engineer design.
Permit Issued
Issued on 11/8/2021
Issuing Office
Current Status
CofO Issued on 5/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2021 APPLICANT
Assigned to Plan Check Engineer 7/29/2021 RAMA DABADGE
Corrections Issued 7/29/2021 RAMA DABADGE
Applicant returned to address corrections 8/26/2021 RAMA DABADGE
Applicant returned to address corrections 10/5/2021 FERNANDO FLORES
Plan Check Approved 10/28/2021 DANIEL SANJUAN
Plan Check Approved 10/28/2021 KHUONG TRUONG
Issued 11/8/2021 APPLICANT
Building Plans Picked Up 11/10/2021 APPLICANT
CofO in Progress 5/27/2022 RICHARD STEINBACH
Permit Finaled 5/27/2022 DANIEL ORRANTE
CofO Issued 5/27/2022 DANIEL ORRANTE
Permit Finaled 5/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/4/2021 RAMA DABADGE
Coastal Zone Cleared 10/20/2021 MAXFIELD VERMY
ZA Case Cleared 10/20/2021 MAXFIELD VERMY

Contact Information

Contractor South Stone Construction; Lic. No.: 456312-B 18202 ALLEGHENY      SANTA ANA, CA 92705
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/27/2021 Corrections Issued ENRIQUE MIRELES
Pre-Gunite 12/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Rough-Plumbing 12/27/2021 Not Ready for Inspection ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 1/21/2022 Approved BOBBY KEY
Grounding or Bonding 1/21/2022 Approved BOBBY KEY
Pool Piping 1/21/2022 Approved BOBBY KEY
Pre-Gunite 1/21/2022 Approved BOBBY KEY
Gas Piping or Gas Test 2/17/2022 Approved BOBBY KEY
Rough-Electrical 2/17/2022 Approved BOBBY KEY
Enclosure/Fence 4/14/2022 Approved BOBBY KEY
Final 5/10/2022 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready BOBBY KEY
Equipment Noise Level 5/17/2022 Approved JAMES VORHIS
Final 5/18/2022 Partial Approval RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 5/18/2022 SGSOV Approved RICHARD STEINBACH
Final 5/24/2022 Conditional Approval BOBBY KEY