6841 W CAMROSE DR 90068
Certificate Information: 6841 W CAMROSE DR 90068
- Application / Permit
- 21047-10000-01624
- Plan Check / Job No.
- B21LA13290
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 3/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2021 | FERNANDO FLORES |
| Corrections Issued | 7/17/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/7/2021 | SHANGQIN XIE |
| Building Plans Picked Up | 10/12/2021 | APPLICANT |
| Plan Check Approved | 10/26/2021 | DANIEL SANJUAN |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 6/15/2022 | BRIAN SULLIVAN |
| Permit Finaled | 3/1/2023 | DANIEL ORRANTE |
| CofO Issued | 3/1/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/1/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/7/2021 | FERNANDO FLORES |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C35 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/13/2021 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 12/13/2021 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Shotcrete | 12/16/2021 | Conditional Approval | BRIAN SULLIVAN |
| Enclosure/Fence | 3/3/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Pool Equipment Noise Test | 4/11/2022 | Conditional Approval | JUSTIN CURTIS |
| Enclosure/Fence | 4/20/2022 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Not Ready | BRIAN SULLIVAN |
| Grounding or Bonding | 5/23/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deck | 6/1/2022 | Conditional Approval | BRIAN SULLIVAN |
| Enclosure/Fence | 6/8/2022 | Approved | BRIAN SULLIVAN |
| Equipment Noise Level | 6/14/2022 | Approved | JUSTIN CURTIS |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Approved | BRIAN SULLIVAN |
| Final | 6/15/2022 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Approved | BRIAN SULLIVAN |