6841 W CAMROSE DR 90068

Certificate Information: 6841 W CAMROSE DR 90068

Application / Permit
21047-10000-01624
Plan Check / Job No.
B21LA13290
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL PER LA CITY STANDARD PLAN #268.
Permit Issued
Issued on 11/1/2021
Issuing Office
Current Status
CofO Issued on 3/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2021 APPLICANT
Assigned to Plan Check Engineer 7/16/2021 FERNANDO FLORES
Corrections Issued 7/17/2021 FERNANDO FLORES
Applicant returned to address corrections 10/7/2021 SHANGQIN XIE
Building Plans Picked Up 10/12/2021 APPLICANT
Plan Check Approved 10/26/2021 DANIEL SANJUAN
Issued 11/1/2021 APPLICANT
CofO in Progress 6/15/2022 BRIAN SULLIVAN
Permit Finaled 3/1/2023 DANIEL ORRANTE
CofO Issued 3/1/2023 DANIEL ORRANTE
Permit Finaled 3/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/7/2021 FERNANDO FLORES

Contact Information

Contractor Premier Pool Plastering; Lic. No.: 625132-C35 14520 FOOTHILL BLVD      SYLMAR, CA 91342
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 12/13/2021 Approved BRIAN SULLIVAN
Special/Order Compliance 12/13/2021 Corrections Issued BRIAN SULLIVAN
Deputy Shotcrete 12/16/2021 Conditional Approval BRIAN SULLIVAN
Enclosure/Fence 3/3/2022 Not Ready for Inspection BRIAN SULLIVAN
Pool Equipment Noise Test 4/11/2022 Conditional Approval JUSTIN CURTIS
Enclosure/Fence 4/20/2022 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready BRIAN SULLIVAN
Grounding or Bonding 5/23/2022 Not Ready for Inspection BRIAN SULLIVAN
Deck 6/1/2022 Conditional Approval BRIAN SULLIVAN
Enclosure/Fence 6/8/2022 Approved BRIAN SULLIVAN
Equipment Noise Level 6/14/2022 Approved JUSTIN CURTIS
Excavation/Setback/Form/Re-Bar 6/15/2022 Approved BRIAN SULLIVAN
Final 6/15/2022 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Approved BRIAN SULLIVAN