15608 W LILLI WAY 91406

Certificate Information: 15608 W LILLI WAY 91406

Application / Permit
21047-10000-01577
Plan Check / Job No.
B21LA12760
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA PER STANDARD PLAN #270.
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 4/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/12/2021 RICARDO RAMIREZ
Corrections Issued 7/12/2021 RICARDO RAMIREZ
Applicant returned to address corrections 8/8/2021 AUNG SOE
Issued 8/24/2021 APPLICANT
Building Plans Picked Up 8/25/2021 APPLICANT
CofO in Progress 3/20/2023 RYAN SALAZAR
CofO Issued 4/11/2023 MICHAEL SMITH
Permit Finaled 4/11/2023 MICHAEL SMITH

Permit Application Clearance Information

"Q" conditions Cleared 7/26/2021 RUBEN VASQUEZ
"T" removal Cleared 7/26/2021 RUBEN VASQUEZ
CPC Cleared 7/26/2021 RUBEN VASQUEZ
Miscellaneous Cleared 7/26/2021 RUBEN VASQUEZ
Miscellaneous Cleared 7/26/2021 RUBEN VASQUEZ

Contact Information

Contractor Home Run Builders Inc; Lic. No.: 850974-B 5102 GOODLAND AVE      VALLEY VILLAGE, CA 91607
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/30/2021 Approved JACK KARGODORIAN
Pre-Gunite 9/30/2021 Approved JACK KARGODORIAN
Rough-Plumbing 9/30/2021 Approved JACK KARGODORIAN
Deputy Shotcrete 10/4/2021 Approved RICHARD DOCKUS
Gunite 10/6/2021 Approved MATTHEW NELSON
Gas Piping or Gas Test 10/20/2021 Approved RICHARD DOCKUS
Grounding or Bonding 10/20/2021 Approved RICHARD DOCKUS
Enclosure/Fence 10/26/2021 Approved RICHARD DOCKUS
Equipment Noise Level 11/12/2021 Approved ALFREDO FLORES
Final 11/22/2021 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 11/22/2021 SGSOV Approved RICHARD DOCKUS
Final 3/21/2023 OK to Issue CofO RYAN SALAZAR