592 N TIGERTAIL ROAD 90049
Certificate Information: 592 N TIGERTAIL ROAD 90049
- Application / Permit
- 21047-10000-01513
- Plan Check / Job No.
- B20LA18228
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool and spa per standard plan # 265
- Permit Issued
- Issued on 5/17/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | SHANGQIN XIE |
| Corrections Issued | 11/10/2020 | SHANGQIN XIE |
| Quality Review Completed | 11/20/2020 | STANLEY RAAP |
| Applicant returned to address corrections | 6/29/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 9/23/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/16/2021 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/12/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 4/18/2022 | SHANGQIN XIE |
| Building Plans Picked Up | 5/9/2022 | APPLICANT |
| Plan Check Approved | 5/17/2023 | SHANGQIN XIE |
| Issued | 5/17/2023 | APPLICANT |
| No Progress | 11/3/2025 | KENNETH NAGLE |
| CofO in Progress | 11/3/2025 | KENNETH NAGLE |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
| CofO Issued | 11/4/2025 | RICHARD STEINBACH |
| Permit Finaled | 11/4/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Oakhill Construction Inc; Lic. No.: 1013979-B | 23679 CALABASAS ROAD 1111 CALABASAS, CA 91302 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 8/22/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 8/23/2023 | Approved | CARLOS MATAMOROS |
| Gunite | 8/23/2023 | Approved | CARLOS MATAMOROS |
| Pool Piping | 8/23/2023 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 8/23/2023 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 8/7/2024 | Partial Approval | CARLOS MATAMOROS |
| Grounding or Bonding | 8/19/2024 | Approved | CARLOS MATAMOROS |
| Pool Piping | 8/19/2024 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 8/23/2024 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 10/11/2024 | Approved | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 10/18/2024 | Corrections Issued | CARLOS MATAMOROS |
| Deputy Shotcrete | 11/14/2024 | No Access for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/15/2024 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 10/15/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/29/2025 | Approved | CARLOS MATAMOROS |
| Final | 10/29/2025 | Partial Approval | CARLOS MATAMOROS |
| Pre-Gunite | 10/29/2025 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 10/31/2025 | Approved | CARLOS MATAMOROS |