4937 W ELMWOOD AVE 90004
Certificate Information: 4937 W ELMWOOD AVE 90004
- Application / Permit
- 21047-10000-01449
- Plan Check / Job No.
- B21LA11821
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Eplan. New swimming pool and spa per city of Los Angeles standard plan # 268.
- Permit Issued
- Issued on 7/24/2021
- Issuing Office
- Current Status
- CofO Issued on 7/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | HELEN NGUYEN |
| Corrections Issued | 6/24/2021 | HELEN NGUYEN |
| Plan Check Approved | 7/1/2021 | HELEN NGUYEN |
| Issued | 7/24/2021 | APPLICANT |
| CofO in Progress | 6/21/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 7/26/2022 | DEROLD HAUFF |
| CofO Issued | 7/26/2022 | DEROLD HAUFF |
| Permit Finaled | 7/26/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | A & E Construction & Painting Inc; Lic. No.: 1014539-C53 | 7330 LASAINE AVENUE VAN NUYS, CA 91406 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 9/1/2021 | Approved | ARTHUR SARGSYAN |
| Deck | 10/12/2021 | Approved | ARTHUR SARGSYAN |
| Enclosure/Fence | 12/14/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 4/14/2022 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Approved | STUART CHAPMAN |
| Final | 4/14/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 4/14/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/14/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Final | 5/4/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 5/4/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 5/9/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 5/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 5/17/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| PLUMBING-Final | 5/17/2022 | Approved | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 5/17/2022 | SGSOV Approved | SHAVONNE ESPINOZA |
| Final | 5/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 5/26/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 6/7/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Pool Equipment Noise Test | 6/13/2022 | Approved | JUSTIN CURTIS |
| Final | 6/20/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |