2031 N ALEXANDRIA AVE 90027
Certificate Information: 2031 N ALEXANDRIA AVE 90027
- Application / Permit
- 21047-10000-01393
- Plan Check / Job No.
- B21LA11357
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL AND SPA WITH BUILT IN SPA AND AUTOMATIC POOL COVER PER ZA-2021-8191-ZAA-F 1 OF 3
- Permit Issued
- Issued on 9/12/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/15/2021 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 7/20/2021 | SAI KHUM |
| Building Plans Picked Up | 7/26/2021 | APPLICANT |
| Plan Check Approved | 9/12/2022 | FARSHAD ALIMOHAMADI |
| Issued | 9/12/2022 | APPLICANT |
| CofO in Progress | 6/30/2023 | JOSEPH MCGARRY |
| Permit Finaled | 7/2/2023 | DEROLD HAUFF |
| CofO Issued | 7/2/2023 | DEROLD HAUFF |
| Permit Finaled | 7/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | THOMAS LANG |
| Highway dedication | Cleared | 8/27/2021 | NAZILA NOORIFAR |
| BHO/Hillside ordinance | Cleared | 12/14/2021 | NAZILA NOORIFAR |
| Miscellaneous | Cleared | 9/8/2022 | SPENCER WEJROWSKI |
| ZA Case | Cleared | 9/8/2022 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Design Management And Construction Services; Lic. No.: 856999-C53 | 26007 HUNTINGTON LANE STE 7 VALENCIA, CA 91355 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/7/2022 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 10/7/2022 | Approved | JOSEPH MCGARRY |
| Pool Piping | 10/7/2022 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 10/7/2022 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 1/12/2023 | Partial Approval | JOSEPH MCGARRY |
| Deck | 2/27/2023 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 5/11/2023 | Conditional Approval | JOSEPH MCGARRY |
| Equipment Noise Level | 6/8/2023 | Approved | JUAN ESCOTO DELGADO |
| Final | 6/12/2023 | Not Ready for Inspection | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 6/12/2023 | SGSOV Approved | JEFFREY MEAD |
| Final | 6/28/2023 | OK to Issue CofO | JOSEPH MCGARRY |