4819 N MURIETTA AVE 91423
Certificate Information: 4819 N MURIETTA AVE 91423
- Application / Permit
- 21047-10000-01350
- Plan Check / Job No.
- B21LA11052
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) 12'x 25' POOL AND 6' X 6' SPA PER STD PLAN #268
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2021 | HERNAN ARREOLA |
| Plan Check Approved | 6/15/2021 | HERNAN ARREOLA |
| Issued | 6/21/2021 | APPLICANT |
| CofO in Progress | 10/6/2021 | MISAEL ESPARZA |
| CofO Issued | 10/6/2021 | MICHAEL SMITH |
| Permit Finaled | 10/6/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 13437 VENTURA BLVD #216 SHERMAN OAKS, CA 91423 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 7/19/2021 | Approved | CHARLES POWELL |
| Grounding or Bonding | 7/19/2021 | Approved | CHARLES POWELL |
| Pool Piping | 7/19/2021 | Approved | CHARLES POWELL |
| Pre-Gunite | 7/19/2021 | Approved | CHARLES POWELL |
| Deck | 8/18/2021 | Corrections Issued | ARAM AVEDISIAN |
| Deck | 8/20/2021 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 9/15/2021 | Approved | MISAEL ESPARZA |
| Equipment Noise Level | 9/23/2021 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 9/23/2021 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 9/27/2021 | SGSOV Not Ready | ARAM AVEDISIAN |
| ELECTRICAL-Final | 10/5/2021 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 10/5/2021 | Approved | MISAEL ESPARZA |
| Final | 10/5/2021 | OK to Issue CofO | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/5/2021 | SGSOV Approved | MISAEL ESPARZA |