232 S AVONDALE AVE 90049

Certificate Information: 232 S AVONDALE AVE 90049

Application / Permit
21047-10000-01308
Plan Check / Job No.
B21LA10777
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL PER ENGINEER DESIGN AND SOIL REPORT.
Permit Issued
Issued on 1/7/2022
Issuing Office
Current Status
CofO Issued on 2/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 7/15/2021 SERGIO GUTIERREZ
Corrections Issued 7/22/2021 SERGIO GUTIERREZ
Quality Review Completed 7/27/2021 ALLEN MANALANSAN
Building Plans Picked Up 7/29/2021 APPLICANT
Plan Check Approved 12/17/2021 SERGIO GUTIERREZ
Issued 1/7/2022 APPLICANT
CofO in Progress 1/30/2023 JESUS RODRIGUEZ
Permit Finaled 2/6/2023 DANIEL ORRANTE
CofO Issued 2/6/2023 DANIEL ORRANTE
Permit Finaled 2/6/2023 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 8/30/2021 PABLO ESTRADA
GPI Written Notices Cleared 12/17/2021 SERGIO GUTIERREZ
Grading Pre-Inspection Cleared 12/17/2021 SERGIO GUTIERREZ

Contact Information

Contractor Valle/Reinis Builders Inc; Lic. No.: 839178-B 11661 SAN VICENTE BLVD STE 302      LOS ANGELES, CA 90049
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2022 Partial Approval JOHN KIDWELL
Pre-Gunite 5/16/2022 Approved JOHN KIDWELL
Grounding or Bonding 10/4/2022 Approved KEVIN SARGSYAN
Enclosure/Fence 10/25/2022 Approved ANDREW NAVE
Excavation/Setback/Form/Re-Bar 11/30/2022 Approved KEVIN SARGSYAN
Final 11/30/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Not Ready KEVIN SARGSYAN
ELECTRICAL-Final 1/27/2023 Approved JESUS RODRIGUEZ
Final 1/27/2023 OK to Issue CofO JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/27/2023 SGSOV Approved JESUS RODRIGUEZ