5631 N GREENBUSH AVE 91401

Certificate Information: 5631 N GREENBUSH AVE 91401

Application / Permit
21047-10000-01271
Plan Check / Job No.
B21LA10429
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL & SPA, STANDARD PLAN #270
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 10/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2021 APPLICANT
Assigned to Plan Check Engineer 6/4/2021 FERNANDO FLORES
Plan Check Approved 6/4/2021 FERNANDO FLORES
Issued 6/8/2021 APPLICANT
Building Plans Picked Up 6/10/2021 APPLICANT
CofO in Progress 9/30/2021 MICHAEL TEMPLE
CofO Issued 10/12/2021 MICHAEL SMITH
Permit Finaled 10/12/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Home Run Builders Inc; Lic. No.: 850974-B 5102 GOODLAND AVE      VALLEY VILLAGE, CA 91607
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/23/2021 Approved ARAM AVEDISIAN
Rough-Electrical 6/28/2021 Approved ARTHUR SARGSYAN
Rough-Plumbing 6/28/2021 Approved ARTHUR SARGSYAN
Deputy Shotcrete 6/30/2021 Conditional Approval ALAN MORELOS
Gunite 7/2/2021 No Access for Inspection ARTHUR SARGSYAN
Enclosure/Fence 7/14/2021 Approved ARTHUR SARGSYAN
Pool Equipment Noise Test 8/11/2021 Approved FELIPE PENICHE
Final 8/20/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/20/2021 SGSOV Not Ready JENNIFER RABUCHIN
Final 9/15/2021 No Access for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/15/2021 SGSOV Not Ready RICHARD DOCKUS
Final 9/17/2021 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/17/2021 SGSOV Approved RICHARD DOCKUS
Final 9/22/2021 Not Ready for Inspection RICHARD DOCKUS
Final 9/24/2021 Corrections Issued RICHARD DOCKUS
Final 9/29/2021 OK to Issue CofO MICHAEL TEMPLE