1117 W ENGLANDER ST 90731
Certificate Information: 1117 W ENGLANDER ST 90731
- Application / Permit
- 21047-10000-01214
- Plan Check / Job No.
- B21LA09949
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL (E) SWIMMING POOL FOR NEW SPA AND BAJA SHELF. WORK PER STANDARD PLAN #268 AND ENGINEERED DESIGN.
- Permit Issued
- Issued on 10/21/2021
- Issuing Office
- Current Status
- CofO Issued on 5/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2021 | GEORGE ALVAREZ |
| Corrections Issued | 6/15/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 8/25/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 9/9/2021 | RAHEL BEYENE |
| Plan Check Approved | 9/23/2021 | RICARDO RAMIREZ |
| Issued | 10/21/2021 | APPLICANT |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| CofO in Progress | 4/26/2022 | ANSON MAGLASANG |
| Permit Finaled | 5/3/2022 | DEROLD HAUFF |
| CofO Issued | 5/3/2022 | DEROLD HAUFF |
| Permit Finaled | 5/3/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 9/9/2021 | JOHN BACON |
| Construction within easement | Cleared | 9/9/2021 | JOHN BACON |
| Grading Pre-Inspection | Cleared | 9/23/2021 | GEORGE ALVAREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/28/2021 | Corrections Issued | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 11/8/2021 | Approved | ANSON MAGLASANG |
| Pre-Gunite | 11/8/2021 | Approved | ANSON MAGLASANG |
| Rough-Electrical | 11/19/2021 | Partial Approval | ANSON MAGLASANG |
| Rough-Plumbing | 11/19/2021 | Not Ready for Inspection | ANSON MAGLASANG |
| Gas Piping or Gas Test | 11/24/2021 | Approved | ANSON MAGLASANG |
| Rough-Electrical | 11/24/2021 | Partial Approval | ANSON MAGLASANG |
| Rough-Plumbing | 11/24/2021 | Corrections Issued | ANSON MAGLASANG |
| Deputy Shotcrete | 11/30/2021 | Approved | JOHN KLARIN |
| Pre-Gunite | 12/1/2021 | Approved | JOHN KLARIN |
| Enclosure/Fence | 4/8/2022 | Corrections Issued | ANSON MAGLASANG |
| Grounding or Bonding | 4/8/2022 | Approved | ANSON MAGLASANG |
| Rough-Plumbing | 4/8/2022 | Approved | ANSON MAGLASANG |
| Enclosure/Fence | 4/12/2022 | Approved | ANSON MAGLASANG |
| Pool Equipment Noise Test | 4/18/2022 | Approved | AGUSTIN ALVAREZMORALES |
| Final | 4/21/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Not Ready | ANSON MAGLASANG |
| Final | 4/25/2022 | OK to Issue CofO | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 4/25/2022 | SGSOV Not Required | ANSON MAGLASANG |