2036 N STRADELLA ROAD 90077

Certificate Information: 2036 N STRADELLA ROAD 90077

Application / Permit
21047-10000-01198
Plan Check / Job No.
B21LA09801
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
2-(N) ELEVATED POOLS
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 7/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 DANIEL YIP
Corrections Issued 7/8/2021 DANIEL YIP
Quality Review Completed 7/15/2021 JASON HEALEY
Building Plans Picked Up 7/26/2021 APPLICANT
Applicant returned to address corrections 9/2/2021 DANIEL YIP
Applicant returned to address corrections 10/29/2021 DANIEL YIP
Plan Check Approved 11/17/2021 DANIEL YIP
Issued 12/2/2021 APPLICANT
CofO in Progress 5/20/2025 CHRISTOPHER WILSON
No Progress 5/24/2025 MICHAEL PELHAM
CofO in Progress 5/24/2025 MICHAEL PELHAM
Permit Finaled 7/7/2025 RICHARD STEINBACH
CofO Issued 7/7/2025 RICHARD STEINBACH
Permit Finaled 7/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/9/2021 DANIEL YIP

Contact Information

Contractor Socal Home Builders Inc; Lic. No.: 1055386-B 13351 RIVERSIDE DRIVE #348      .SHERMAN OAKS, CA 91423

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 5/3/2022 Conditional Approval CHRISTOPHER WILSON
Deputy Other (see comments) 5/4/2022 Conditional Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/6/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 5/6/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/13/2022 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 6/14/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 7/21/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/8/2022 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/23/2022 Partial Approval CHRISTOPHER WILSON
Deputy Other (see comments) 9/29/2022 Conditional Approval MICHAEL PELHAM
Deputy Other (see comments) 10/3/2022 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 10/3/2022 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 10/3/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Shotcrete 10/7/2022 Conditional Approval CHRISTOPHER WILSON
Pre-Gunite 11/4/2022 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 11/9/2022 Partial Approval CHRISTOPHER WILSON
Pool Piping 11/9/2022 Approved CHRISTOPHER WILSON
Pre-Gunite 11/9/2022 Approved CHRISTOPHER WILSON
Rough-Electrical 11/9/2022 Partial Approval CHRISTOPHER WILSON
Rough-Plumbing 11/9/2022 Partial Approval CHRISTOPHER WILSON
Deputy Shotcrete 11/15/2022 Conditional Approval MICHAEL PELHAM
Deputy Drilled-In Anchors 11/22/2022 Conditional Approval DANIEL ORRANTE
Excavation/Setback/Form/Re-Bar 11/22/2022 Partial Approval CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 12/27/2022 Partial Approval CHRISTOPHER WILSON
Pool/Spa Cover 3/7/2023 Corrections Issued CHRISTOPHER WILSON
Pre-Gunite 3/13/2023 Approved GERMAN RODRIGUEZ MENDOZA
Deputy Shotcrete 3/17/2023 Conditional Approval MICHAEL PELHAM
Enclosure/Fence 1/2/2025 Corrections Issued CHRISTOPHER WILSON
Enclosure/Fence 1/7/2025 Approved MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 3/4/2025 Approved CARLOS MATAMOROS
Final 3/4/2025 Corrections Issued CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/4/2025 SGSOV Approved CARLOS MATAMOROS
Final 5/19/2025 OK to Issue CofO CHRISTOPHER WILSON
Special/Order Compliance 6/3/2025 No Access for Inspection CHRISTOPHER WILSON
Special/Order Compliance 6/9/2025 Corrections Issued CHRISTOPHER WILSON