1769 S BEDFORD ST 90035
Certificate Information: 1769 S BEDFORD ST 90035
- Application / Permit
- 21047-10000-01042
- Plan Check / Job No.
- B21LA08878
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL WITH SPA AND POOL EQUIPEMENT INSTALLATION
- Permit Issued
- Issued on 10/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2021 | CARLOS MONTES |
| Corrections Issued | 5/13/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 7/15/2021 | CARLOS MONTES |
| Plan Check Approved | 7/21/2021 | CARLOS MONTES |
| Issued | 10/5/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | EVAN COOPER |
| CofO in Progress | 8/16/2022 | EVAN COOPER |
| Permit Finaled | 8/18/2022 | DANIEL ORRANTE |
| CofO Issued | 8/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/2/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Art'S Pool Plastering & Remodeling; Lic. No.: 906751-C53 | 8504 CEYLON AVENUE PICO RIVERA, CA 90660 |
| Engineer | Cristescu,, Barbu D; Lic. No.: C72038 | 14401 SYLVAN STREET 209 VAN NUYS, CA 91401 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/7/2021 | Approved | EVAN COOPER |
| Pre-Gunite | 10/19/2021 | Approved | JUAN VALENZUELA |
| Deck | 2/1/2022 | Approved | EVAN COOPER |
| Pre-Gunite | 2/1/2022 | Approved | EVAN COOPER |
| Enclosure/Fence | 3/9/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/1/2022 | SGSOV Not Ready | EVAN COOPER |
| Pool Equipment Noise Test | 8/4/2022 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 8/16/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 8/16/2022 | Approved | EVAN COOPER |
| Final | 8/16/2022 | OK to Issue CofO | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | EVAN COOPER |