141 N BARRINGTON AVE 90049

Certificate Information: 141 N BARRINGTON AVE 90049

Application / Permit
21047-10000-00986
Plan Check / Job No.
B21LA08310
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW SWIMMING POOL AND SPA
Permit Issued
Issued on 8/12/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 JOE VO
Corrections Issued 5/26/2021 JOE VO
Quality Review Completed 6/1/2021 KEN GILL
Plan Check Approved 7/26/2021 JOE VO
Issued 8/12/2021 APPLICANT
Building Plans Picked Up 8/18/2021 APPLICANT
CofO in Progress 11/15/2022 CARLOS MATAMOROS
CofO in Progress 11/15/2022 CARLOS MATAMOROS
Permit Finaled 12/17/2022 DANIEL ORRANTE
CofO Issued 12/17/2022 DANIEL ORRANTE
Permit Finaled 12/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Hartman Baldwin Inc; Lic. No.: 653340-B 100 WEST FOOTHILL BLVD      CLAREMONT, CA 91711
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/24/2022 Partial Approval CARLOS MATAMOROS
Grounding or Bonding 3/24/2022 Corrections Issued CARLOS MATAMOROS
Pool Piping 3/24/2022 Approved CARLOS MATAMOROS
Pre-Gunite 3/24/2022 Partial Approval CARLOS MATAMOROS
Gas Piping or Gas Test 6/24/2022 Approved CARLOS MATAMOROS
Rough-Electrical 6/24/2022 Approved CARLOS MATAMOROS
Enclosure/Fence 8/30/2022 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 8/30/2022 Approved STEPHANIE SWANSON
Pre-Gunite 8/30/2022 Approved STEPHANIE SWANSON
Special/Order Compliance 8/30/2022 Partial Inspection MICHAEL PELHAM
Deck 9/1/2022 Approved MICHAEL PELHAM
Enclosure/Fence 9/1/2022 Approved MICHAEL PELHAM
Final 9/7/2022 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Not Ready CARLOS MATAMOROS
Final 9/29/2022 Conditional Approval MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 9/29/2022 SGSOV Approved MICHAEL PELHAM
Final 11/4/2022 OK to Issue CofO CARLOS MATAMOROS