6169 E ROY ST 90042

Certificate Information: 6169 E ROY ST 90042

Application / Permit
21047-10000-00933
Plan Check / Job No.
B21LA07459
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16'-0" X 12'-0" POOL AND 8'-0" X 6'-0" SPA PER STANDARD PLAN 268.
Permit Issued
Issued on 10/27/2021
Issuing Office
Current Status
CofO Issued on 10/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 STANLEY RAAP
Corrections Issued 4/27/2021 STANLEY RAAP
Applicant returned to address corrections 9/29/2021 RAHEL BEYENE
Applicant returned to address corrections 10/10/2021 AUNG SOE
Plan Check Approved 10/12/2021 AUNG SOE
Issued 10/27/2021 APPLICANT
Building Plans Picked Up 11/1/2021 APPLICANT
CofO in Progress 10/7/2022 AMY COLIN
Permit Finaled 10/14/2022 DEROLD HAUFF
CofO Issued 10/14/2022 DEROLD HAUFF
Permit Finaled 10/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/29/2021 STANLEY RAAP

Contact Information

Contractor Blue Fountain Pools And Spas Inc; Lic. No.: 1004554-C53 1151 S GRAND AVE      GLENDORA, CA 91740
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 2/23/2022 Corrections Issued COREY HUPP
Rough-Plumbing 2/23/2022 Not Ready for Inspection COREY HUPP
Pre-Gunite 3/2/2022 Partial Inspection COREY HUPP
Rough-Plumbing 3/2/2022 Not Ready for Inspection COREY HUPP
Pre-Gunite 4/15/2022 Approved AMY COLIN
Rough-Plumbing 4/15/2022 Approved AMY COLIN
Rough-Electrical 4/29/2022 Approved AMY COLIN
Rough-Electrical 5/6/2022 Approved AMY COLIN
Enclosure/Fence 6/24/2022 Corrections Issued AMY COLIN
Enclosure/Fence 7/1/2022 Partial Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 9/30/2022 Approved AMY COLIN
Final 9/30/2022 Corrections Issued AMY COLIN
Pool Equipment Noise Test 9/30/2022 Approved JUSTIN CURTIS
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Not Ready AMY COLIN
Final 10/3/2022 Partial Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved AMY COLIN
Final 10/7/2022 OK to Issue CofO AMY COLIN