2920 W ANGUS ST 90039

Certificate Information: 2920 W ANGUS ST 90039

Application / Permit
21047-10000-00897
Plan Check / Job No.
B21LA07574
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 13' X 30', 6.5' DEEP POOL WITH 5'6" X 12'0" SPA WITHIN POOL , AND AUTOMATIC POOL COVER 1 OF 2
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Assigned to Plan Check Engineer 4/23/2021 STANLEY RAAP
Corrections Issued 4/27/2021 STANLEY RAAP
Applicant returned to address corrections 7/10/2021 ZAW HAN
Plan Check Approved 7/12/2021 ZAW HAN
Issued 7/26/2021 APPLICANT
Building Plans Picked Up 7/27/2021 APPLICANT
CofO in Progress 4/30/2022 JOSEPH MCGARRY
Permit Finaled 5/4/2022 DEROLD HAUFF
Permit Finaled 5/4/2022 DEROLD HAUFF
CofO Issued 5/4/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/14/2021 CECILIO NAVARRO
Sewer availability Cleared 5/17/2021 CECILIO NAVARRO
Excavation more than 5-ft deep Cleared 7/9/2021 CALOSHA APPROVED
Grading Pre-Inspection Cleared 7/9/2021 ALEXANDER HELFER

Contact Information

Contractor Design Management And Construction Services; Lic. No.: 856999-B 26007 HUNTINGTON LANE STE 7      VALENCIA, CA 91355
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/30/2021 Approved JOSEPH MCGARRY
Gas Piping or Gas Test 8/30/2021 Partial Approval JOSEPH MCGARRY
Grounding or Bonding 8/30/2021 Approved JOSEPH MCGARRY
Pool Piping 8/30/2021 Approved JOSEPH MCGARRY
Pre-Gunite 8/30/2021 Approved JOSEPH MCGARRY
Deputy Shotcrete 9/8/2021 Partial Approval JOSEPH MCGARRY
Gas Piping or Gas Test 9/30/2021 Approved JOSEPH MCGARRY
Pool Piping 9/30/2021 Approved JOSEPH MCGARRY
Rough-Electrical 9/30/2021 Approved JOSEPH MCGARRY
Rough-Plumbing 9/30/2021 Approved JOSEPH MCGARRY
Deck 11/1/2021 Approved JOSEPH MCGARRY
Enclosure/Fence 2/18/2022 Approved JOSEPH MCGARRY
Final 4/21/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 4/21/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Pool Equipment Noise Test 4/22/2022 Approved ROBERT CHAVEZ
Final 4/29/2022 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/29/2022 SGSOV Approved JOSEPH MCGARRY