3716 N PRESTWICK DR 90027
Certificate Information: 3716 N PRESTWICK DR 90027
- Application / Permit
- 21047-10000-00855
- Plan Check / Job No.
- B21LA07191
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED POOL AND SPA PER L.A. CITY STANDARD #268 WITH PORTION OF POOL FREE-STANDING FACING DESCENDING SLOPE. SEE ENGINEER'S DETAILS.
- Permit Issued
- Issued on 5/17/2021
- Issuing Office
- Current Status
- CofO Issued on 4/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/26/2021 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/28/2021 | APPLICANT |
| Plan Check Approved | 5/5/2021 | LAMAR DAVIS |
| Issued | 5/17/2021 | APPLICANT |
| CofO in Progress | 3/31/2022 | JOSEPH MCGARRY |
| Permit Finaled | 4/5/2022 | RONALD MYRICK |
| CofO Issued | 4/5/2022 | RONALD MYRICK |
| Permit Finaled | 4/5/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/7/2021 | ROBERT HUGHES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/2/2021 | Partial Approval | JOSEPH MCGARRY |
| Pool Piping | 6/9/2021 | Approved | HAMIK HARTOUNIAN |
| Pre-Gunite | 6/9/2021 | Approved | HAMIK HARTOUNIAN |
| Rough-Plumbing | 6/9/2021 | Approved | HAMIK HARTOUNIAN |
| Special/Order Compliance | 11/30/2021 | Approved | JOSEPH MCGARRY |
| Deck | 1/27/2022 | Partial Approval | JOSEPH MCGARRY |
| Enclosure/Fence | 1/27/2022 | Corrections Issued | JOSEPH MCGARRY |
| Deck | 2/10/2022 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 2/10/2022 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Final | 2/10/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/31/2022 | Approved | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 3/31/2022 | Approved | JOSEPH MCGARRY |
| Final | 3/31/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| PLUMBING-Final | 3/31/2022 | Approved | JOSEPH MCGARRY |
| Pool Piping | 3/31/2022 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | JOSEPH MCGARRY |