4849 N STERN AVE 91423
Certificate Information: 4849 N STERN AVE 91423
- Application / Permit
- 21047-10000-00767
- Plan Check / Job No.
- B21LA06414
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- eplan. Build New Pool & Spa License # - 1046115 Class - C53 Tax ID - 3086745
- Permit Issued
- Issued on 5/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2021 | CARLOS MONTES |
| Corrections Issued | 4/16/2021 | CARLOS MONTES |
| Plan Check Approved | 4/28/2021 | CARLOS MONTES |
| Issued | 5/5/2021 | APPLICANT |
| CofO in Progress | 8/19/2022 | ARAM AVEDISIAN |
| CofO Issued | 8/23/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/23/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/24/2021 | WALTER RAMIREZ |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-C53 | 13437 VENTURA BLVD #216 SHERMAN OAKS, CA 91423 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 8/16/2021 | Approved | JOHN HAYES |
| Special/Order Compliance | 8/16/2021 | Approved | JOHN HAYES |
| Deputy Shotcrete | 8/18/2021 | Conditional Approval | MICHAEL PELHAM |
| Deck | 10/15/2021 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 1/12/2022 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 1/18/2022 | Conditional Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 1/25/2022 | Approved | MISAEL ESPARZA |
| Final | 1/25/2022 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Approved | MISAEL ESPARZA |
| Equipment Noise Level | 2/10/2022 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 2/10/2022 | Approved | FELIPE PENICHE |
| Final | 2/11/2022 | No Access for Inspection | MISAEL ESPARZA |
| Final | 8/11/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/19/2022 | OK to Issue CofO | ARAM AVEDISIAN |