12056 N GOTHIC AVE 91344

Certificate Information: 12056 N GOTHIC AVE 91344

Application / Permit
21047-10000-00731
Plan Check / Job No.
B21LA06121
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL 32' X 18' PER LA CITY STANDARD PLAN #268 NEW SPA 8' DIAMETER (1/2 FLUSH INSIDE POOL) TOTAL POOL AND SPA SURFACE AREA 551 SQFT. ROCK FORMATION 87 SQFT MAX
Permit Issued
Issued on 6/26/2021
Issuing Office
Current Status
CofO Issued on 3/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2021 APPLICANT
Assigned to Plan Check Engineer 4/7/2021 SAMUEL GONZALEZ
Corrections Issued 4/7/2021 SAMUEL GONZALEZ
Issued 6/26/2021 APPLICANT
Building Plans Picked Up 7/6/2021 APPLICANT
CofO in Progress 3/5/2022 MICHAEL TEMPLE
Permit Finaled 3/16/2022 RONALD MYRICK
CofO Issued 3/16/2022 RONALD MYRICK
Permit Finaled 3/16/2022 RONALD MYRICK

Permit Application Clearance Information

Construction near power lines Cleared 5/26/2021 RIDWAN HARDY
Grading Pre-Inspection Cleared 6/22/2021 SAMUEL GONZALEZ

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 2646 DUPONT DR STE 60 #348      IRVINE, CA 92612

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pool Piping 10/26/2021 Approved MARK JOHNSON
Pre-Gunite 10/26/2021 Corrections Issued MARK JOHNSON
Pre-Gunite 10/29/2021 Approved MARK JOHNSON
Deputy Shotcrete 11/9/2021 Conditional Approval MARK JOHNSON
Deck 12/29/2021 Approved MICHEL ABAJAN
Grounding or Bonding 12/29/2021 Approved MICHEL ABAJAN
Enclosure/Fence 1/14/2022 Not Ready for Inspection MARK JOHNSON
Enclosure/Fence 2/1/2022 Corrections Issued JESUS RODRIGUEZ
Enclosure/Fence 2/7/2022 Approved RAUL OLAGI
Equipment Noise Level 2/14/2022 Approved ALFREDO FLORES
Pool Equipment Noise Test 2/14/2022 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 2/17/2022 Approved RAUL OLAGI
Final 2/17/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Not Ready RAUL OLAGI
Final 2/25/2022 OK to Issue CofO MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 2/25/2022 SGSOV Approved MICHAEL TEMPLE