14550 W GREENLEAF ST 91403

Certificate Information: 14550 W GREENLEAF ST 91403

Application / Permit
21047-10000-00717
Plan Check / Job No.
B21LA05991
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
Alteration to (E) pool to include new spa and baja without changing the pool shell using standard plan #268 and raising the pool floor.
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 3/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2021 APPLICANT
Assigned to Plan Check Engineer 4/5/2021 RAMA DABADGE
Corrections Issued 4/7/2021 RAMA DABADGE
Applicant returned to address corrections 5/11/2021 JESSE JIMENEZ
Plan Check Approved 5/21/2021 FERNANDO FLORES
Issued 5/25/2021 APPLICANT
Building Plans Picked Up 5/27/2021 APPLICANT
CofO in Progress 3/31/2022 DANIEL ORRANTE
Permit Finaled 3/31/2022 DANIEL ORRANTE
CofO Issued 3/31/2022 DANIEL ORRANTE
Permit Finaled 3/31/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/7/2021 KIRK LINKLATER
ZA Case Cleared 5/7/2021 DANG NGUYEN

Contact Information

Contractor S & S Pools Inc; Lic. No.: 1073138-C53 14173 ASTORIA STREET      SYLMAR, CA 91324
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deck 6/4/2021 Not Ready for Inspection MICHEL ABAJAN
Enclosure/Fence 6/4/2021 Not Ready for Inspection MICHEL ABAJAN
Gas Piping or Gas Test 6/4/2021 Approved MICHEL ABAJAN
Grounding or Bonding 6/4/2021 Approved MICHEL ABAJAN
Gunite 6/4/2021 Approved MICHEL ABAJAN
PLUMBING-Final 6/4/2021 Partial Inspection MICHEL ABAJAN
Pool Piping 6/4/2021 Approved MICHEL ABAJAN
Pre-Gunite 6/4/2021 Approved MICHEL ABAJAN
Pre-Inspection 6/4/2021 Partial Inspection MICHEL ABAJAN
Deck 6/11/2021 Approved CHARLES POWELL
Enclosure/Fence 6/11/2021 Approved CHARLES POWELL
Final 7/20/2021 Corrections Issued CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 7/20/2021 SGSOV Approved CHARLES POWELL
Final 7/22/2021 Partial Approval CHARLES POWELL