1166 E MONTECITO DR 90031
Certificate Information: 1166 E MONTECITO DR 90031
- Application / Permit
- 21047-10000-00703
- Plan Check / Job No.
- B21LA05808
- Group
- Building
- Type
- Nonbldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW 42' X 28' ELEVATED DECK, WOOD DECK SUPPORTED ON PILES AND GRADE BEAMS.
- Permit Issued
- Issued on 6/7/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/17/2021
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 4/15/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 4/20/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 4/21/2021 | APPLICANT |
| Applicant returned to address corrections | 6/1/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 6/7/2021 | ARSALAN SHABESTARI |
| Issued | 6/7/2021 | APPLICANT |
| Permit Finaled | 10/28/2021 | OSVALDO PARAMO |
| CofO in Progress | 11/15/2021 | OSVALDO PARAMO |
| CofO in Progress | 11/15/2021 | OSVALDO PARAMO |
| No Progress | 11/17/2021 | CHARLES BOGHOSKHAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2021 | CELINA MORENO |
| Grading Pre-Inspection | Cleared | 4/23/2021 | PATRICK MISCHLICH |
| "D" conditions | Cleared | 4/27/2021 | KENTON TRINH |
| "Q" conditions | Cleared | 4/27/2021 | KENTON TRINH |
| Low Impact Development | Cleared | 5/27/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 6/1/2021 | AVALYN KAMACHI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
| Engineer | Noorzay,, Maihan; Lic. No.: GE3085 | 16817 RAINY VALE AVE RIVERSIDE, CA 92503 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2021 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/17/2021 | Corrections Issued | OSVALDO PARAMO |
| Piling/Pier/Caisson | 6/17/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 6/17/2021 | Partial Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 6/24/2021 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/24/2021 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 6/24/2021 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/25/2021 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 6/25/2021 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 6/29/2021 | Approved | RONALD KIDWELL |
| Footing/Foundation/Slab | 7/8/2021 | Partial Approval | OSVALDO PARAMO |
| Reinforced Concrete Frame | 7/8/2021 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 7/9/2021 | Partial Approval | OSVALDO PARAMO |
| Special/Order Compliance | 7/14/2021 | Approved | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 7/21/2021 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/21/2021 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 7/22/2021 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 8/4/2021 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 8/9/2021 | Corrections Issued | OSVALDO PARAMO |
| Drywall Nailing | 8/11/2021 | Approved | OSVALDO PARAMO |
| Final | 8/17/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 8/24/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 10/12/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Structural Steel Frame | 10/18/2021 | Approved | OSVALDO PARAMO |
| Final | 10/28/2021 | Permit Finaled | OSVALDO PARAMO |