1166 E MONTECITO DR 90031

Certificate Information: 1166 E MONTECITO DR 90031

Application / Permit
21047-10000-00703
Plan Check / Job No.
B21LA05808
Group
Building
Type
Nonbldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW 42' X 28' ELEVATED DECK, WOOD DECK SUPPORTED ON PILES AND GRADE BEAMS.
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
Permit Finaled on 11/17/2021

Permit Application Status History

Submitted 3/30/2021 APPLICANT
Assigned to Plan Check Engineer 4/8/2021 ARSALAN SHABESTARI
Corrections Issued 4/15/2021 ARSALAN SHABESTARI
Quality Review Completed 4/20/2021 MICHAEL PEREZ
Building Plans Picked Up 4/21/2021 APPLICANT
Applicant returned to address corrections 6/1/2021 ARSALAN SHABESTARI
Plan Check Approved 6/7/2021 ARSALAN SHABESTARI
Issued 6/7/2021 APPLICANT
Permit Finaled 10/28/2021 OSVALDO PARAMO
CofO in Progress 11/15/2021 OSVALDO PARAMO
CofO in Progress 11/15/2021 OSVALDO PARAMO
No Progress 11/17/2021 CHARLES BOGHOSKHAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/20/2021 CELINA MORENO
Grading Pre-Inspection Cleared 4/23/2021 PATRICK MISCHLICH
"D" conditions Cleared 4/27/2021 KENTON TRINH
"Q" conditions Cleared 4/27/2021 KENTON TRINH
Low Impact Development Cleared 5/27/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/1/2021 AVALYN KAMACHI

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316
Engineer Noorzay,, Maihan; Lic. No.: GE3085 16817 RAINY VALE AVE      RIVERSIDE, CA 92503

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/16/2021 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/17/2021 Corrections Issued OSVALDO PARAMO
Piling/Pier/Caisson 6/17/2021 Not Ready for Inspection OSVALDO PARAMO
Special/Order Compliance 6/17/2021 Partial Inspection BRAD BESCOS
Excavation/Setback/Form/Re-Bar 6/24/2021 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 6/24/2021 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 6/24/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/25/2021 Partial Approval OSVALDO PARAMO
Piling/Pier/Caisson 6/25/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 6/29/2021 Approved RONALD KIDWELL
Footing/Foundation/Slab 7/8/2021 Partial Approval OSVALDO PARAMO
Reinforced Concrete Frame 7/8/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 7/9/2021 Partial Approval OSVALDO PARAMO
Special/Order Compliance 7/14/2021 Approved ELMER BLAND
Excavation/Setback/Form/Re-Bar 7/21/2021 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/21/2021 Partial Approval OSVALDO PARAMO
Deputy Reinf. Concrete 7/22/2021 Partial Approval OSVALDO PARAMO
Wood Frame 8/4/2021 Approved OSVALDO PARAMO
Drywall Nailing 8/9/2021 Corrections Issued OSVALDO PARAMO
Drywall Nailing 8/11/2021 Approved OSVALDO PARAMO
Final 8/17/2021 Not Ready for Inspection OSVALDO PARAMO
Final 8/24/2021 Not Ready for Inspection OSVALDO PARAMO
Final 10/12/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Structural Steel Frame 10/18/2021 Approved OSVALDO PARAMO
Final 10/28/2021 Permit Finaled OSVALDO PARAMO