4647 N TALOFA AVE 91602
Certificate Information: 4647 N TALOFA AVE 91602
- Application / Permit
- 21047-10000-00695
- Plan Check / Job No.
- B21LA05722
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- ePlan. PROPOSED SWIMMING POOL AND SPA.
- Permit Issued
- Issued on 4/30/2021
- Issuing Office
- Current Status
- Issued on 4/30/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/5/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 4/5/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/27/2021 | CRYSTEL MAALOUF |
| Issued | 4/30/2021 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/17/2021 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 12/17/2021 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 12/17/2021 | Conditional Approval | ARAM AVEDISIAN |
| Pre-Gunite | 12/17/2021 | Corrections Issued | ARAM AVEDISIAN |
| Deputy Shotcrete | 1/3/2022 | No Result Entered | RAYMOND KEHOE |
| Gas Piping or Gas Test | 2/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Grounding or Bonding | 2/28/2022 | Not Ready for Inspection | CALEB MEISTER |
| Gas Piping or Gas Test | 3/4/2022 | Approved | JACK KARGODORIAN |
| Grounding or Bonding | 3/4/2022 | Approved | JACK KARGODORIAN |
| Enclosure/Fence | 3/17/2022 | Corrections Issued | MICHAEL TEMPLE |
| Enclosure/Fence | 3/24/2022 | Corrections Issued | ARAM AVEDISIAN |
| Enclosure/Fence | 3/29/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 4/28/2022 | Corrections Issued | RICHARD DOCKUS |
| Pre-Gunite | 4/28/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/28/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Final | 5/2/2022 | Corrections Issued | MICHAEL TEMPLE |
| Pre-Gunite | 5/2/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Approved | MICHAEL TEMPLE |