3964 N SUMAC DR 91403

Certificate Information: 3964 N SUMAC DR 91403

Application / Permit
21047-10000-00646
Plan Check / Job No.
B21LA05305
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
ADD NEW 8'-1"X8'-1" JACUZZI (40" MAX HIGH) 3 OF 3
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO Issued on 11/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/23/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 CHUNG-WEN CHUANG
Corrections Issued 5/13/2021 CHUNG-WEN CHUANG
Quality Review Completed 5/25/2021 JASON HEALEY
Building Plans Picked Up 5/27/2021 APPLICANT
Applicant returned to address corrections 8/4/2021 CHUNG-WEN CHUANG
Applicant returned to address corrections 11/23/2021 CHUNG-WEN CHUANG
Plan Check Approved 1/4/2022 CHUNG-WEN CHUANG
Issued 1/14/2022 APPLICANT
CofO in Progress 11/6/2023 THOMAS FINNILA
CofO in Progress 11/6/2023 THOMAS FINNILA
Permit Finaled 11/25/2023 RUBEN SALAS
CofO Issued 11/25/2023 RUBEN SALAS
Permit Finaled 11/25/2023 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 6/29/2021 WALTER RAMIREZ
Sewer availability Cleared 10/12/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 10/13/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 11/3/2021 ALEXANDER HELFER

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/8/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/14/2022 Corrections Issued JACK KARGODORIAN
Gas Piping or Gas Test 4/14/2022 Partial Approval JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 4/28/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 6/7/2022 Corrections Issued JACK KARGODORIAN
Rough-Electrical 6/7/2022 Partial Approval JACK KARGODORIAN
Deputy Shotcrete 7/22/2022 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 7/25/2022 Corrections Issued JACK KARGODORIAN
Grounding or Bonding 7/25/2022 Partial Approval JACK KARGODORIAN
Pool Piping 7/25/2022 Approved JACK KARGODORIAN
Pre-Gunite 7/25/2022 Not Ready for Inspection JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 7/28/2022 Approved JACK KARGODORIAN
Gunite 7/28/2022 Approved JACK KARGODORIAN
Rough-Plumbing 7/28/2022 Approved JACK KARGODORIAN
Enclosure/Fence 11/15/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 9/18/2023 No Access for Inspection MISAEL ESPARZA
Pre-Gunite 9/18/2023 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/18/2023 SGSOV Not Ready MISAEL ESPARZA
Final 9/25/2023 Corrections Issued THOMAS FINNILA
Pre-Gunite 9/25/2023 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 9/25/2023 SGSOV Not Ready THOMAS FINNILA
Final 11/3/2023 OK to Issue CofO THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved THOMAS FINNILA